Construction payment: notices, deadlines, interest, retention and adjudication, for subcontractors chasing what they are owed.
Get Paid6 min
Late payment interest rate UK: how the 8% over base rule works, and why the date matters
UK late payment interest is 11.75% for business invoices due from 1 July 2026. How it is set, the £40/£70/£100 fixed sums, and a worked example on £18,400.
Priya · Fulcrum editorial
Get Paid7 min
Which main contractors pay late? What the payment practices register says
Ten UK main contractors' filed payment figures: average days to pay, share paid late, report links. Median of 1,496 construction filers: 31 days, 14% late.
Tomasz · Fulcrum editorial
Get Paid5 min
Retention in construction: how to get it back
Retention in construction is contractual, so your subcontract dates decide when to chase. Steps, a plain release email, and what to do when they go quiet.
Gemma · Fulcrum editorial
Get Paid6 min
Payment notice vs pay less notice: which one decides what you get paid
Payment notice vs pay less notice under the Construction Act: who gives each, when, what it must say, and which one decides the sum you are paid. With dates.
Owen · Fulcrum editorial
Get Paid7 min
Pay less notice: what it must say and when it must arrive
What a pay less notice must contain under s.111 of the Construction Act, the deadline (contract or 7 days before the final date), and what happens if it's late.
Owen · Fulcrum editorial