Saipem Ltd: how it pays its suppliers, from its own filing

Saipem Ltd reports paying its suppliers in an average of 57 days, with 32% of invoices paid later than the agreed terms, for the period 1 January 2026 to 30 June 2026. Across the 1,496 companies that report on construction contracts, the median is 31 days and 14% late. Every figure below is the company’s own, approved by a director and published on the government register; this page reproduces it and says what it means for a subcontractor.

57 days

Average days to pay

longer than 91% of the 1,496 filers; median 31 days

32%

Paid later than agreed

a higher share than 82% of filers; median 14%

33%

Paid within 30 days

19% took longer than 60 days

The terms it declares

Standard payment terms
0 to 90 days
Maximum contractual period
90 days
Paid in 31 to 60 days
48%
Paid after 60 days
19%
Not paid because of a dispute
12%
Filed on
29 July 2026

Their standard terms, in their words

Saipem Limited’s standard payment terms are 60 days from receipt of invoice. Supplier payment terms are generally negotiated “back to back” with our main client payment terms which are defined by project, these are usually 30, 45 or 60 days therefore shorter payment terms than 60 days can be agreed.

Every filing since Jun 2024

Saipem Ltd has filed 5 times. The share paid late is down 2 points on the previous filing, and the average days to pay up 4 days. The first filing, for the period to 30 June 2024, reported 62 days and 72% late.

Saipem Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H1 240%37.5%75%0d45d90dH1 24H2 24H1 25H2 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
The last six filings by Saipem Ltd
Period toDays to payPaid lateWithin 30 daysOver 60 days
30 June 20265732%33%19%
31 December 20255334%29%21%
30 June 20255535%21%18%
31 December 20245954%16%31%
30 June 20246272%12%43%

Retention

Retention clauses in construction contracts
yes
Standard retention rate
not stated
In all construction contracts
no
Same terms they receive from their own client
no
When they apply retention
Retention clauses are included only in qualifying contracts with suppliers where specific circumstances justify their use. The principal reasons for applying retention are where a vendor is unable to provide a performance bond for the duration of the contract, or where the vendor risk assessment indicates that additional security is required.

What this means if you are pricing work for them

The share paid later than agreed is the number to read first, because a short term makes an invoice late sooner and a long one hides lateness inside the term. Saipem Ltd is above the median on that measure, so build the delay into your cash flow before you sign. The average days to pay sits over the median.

A worked example on a 30-day term: an invoice of £10,000.00 paid on this company’s average, 27 days after the final date, carries £86.92 of statutory interest at 11.75% plus the fixed sum, £186.92 in all, which the law lets you add without a clause. Run your own figures.

Against the official benchmark: the Department for Business and Trade’s statistics for 2025, published 14 July 2026, put large construction businesses at 33 days to pay with 14% of invoices late by number (13% by value), and all large businesses at 32 days and 15% late. Saipem Ltd is slower than the sector figure. Its late share is above the sector figure.

What the register does not show: it is self-reported, large companies only, and the filing covers the whole company, not your contract. Read it alongside the notice rules that decide what you are actually owed, and keep your own dates.

Questions subcontractors ask about Saipem Ltd

How long does Saipem Ltd take to pay its suppliers?
Saipem Ltd reported an average of 57 days to pay an invoice for 1 January 2026 to 30 June 2026, with 33% of invoices paid within 30 days and 19% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
Does Saipem Ltd pay late?
By its own filing, 32% of Saipem Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is down 2 points on its previous filing (34% for the period to 31 December 2025).
Does Saipem Ltd hold retention?
Yes. Saipem Ltd declares retention clauses in its construction contracts, though not in all of them. The filing's own wording is quoted above.
Can I charge Saipem Ltd interest on a late invoice?
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.

Source: the company’s own report on the government’s payment practices service, report 114724, made under the Reporting on Payment Practices and Performance Regulations 2017 and reproduced under the Open Government Licence v3.0. Register copy taken 2 October 2026; comparisons are against the latest filing of each of the 1,496 companies declaring construction contracts. Figures are as filed, not judged. Not legal advice.