Supplier payment record · 08568552

Winnington Chp Ltd

Reported period: –

View the government filing

Average time to pay

58 days

Register median: 31 days

Invoices paid late

33%

Register median: 14%

Standard payment terms

0 days

Declared in this filing

These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.

Already waiting for payment?

Check your own invoice.

Use your amount and dates to estimate late-payment interest and fixed compensation.

16 filings

How payments have changed

Late payments unchangedCompared with the previous filing

Winnington Chp Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H2 180%37.5%75%0d75d150dH2 18H2 19H2 20H2 21H1 22H2 23H2 24H2 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
View 6 recent filings
Recent payment filings by Winnington Chp Ltd
Period endingDays to payPaid lateWithin 30 daysOver 60 days
31 March 20265819%20%48%
30 September 20255833%20%46%
31 March 20256033%14%56%
30 September 20246926%14%63%
31 March 202412437%16%65%
30 September 20237459%13%68%

More from the filing

Payment terms and invoice breakdown
Standard payment terms
0 days
Maximum contractual period
63 days
Paid within 30 days
20%
Paid in 31–60 days
34%
Paid after 60 days
46%
Not paid because of a dispute
0%

The company’s own wording

End of second month following month of invoice plus 3 days (63 days)
RetentionNone declared

No retention clauses were declared in this filing.

Common questions

How long does Winnington Chp Ltd take to pay its suppliers?

Winnington Chp Ltd reported an average of 58 days to pay an invoice for 1 April 2025 to 30 September 2025, with 20% of invoices paid within 30 days and 46% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.

Does Winnington Chp Ltd pay late?

By its own filing, 33% of Winnington Chp Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is unchanged on its previous filing (33% for the period to 31 March 2025).

Does Winnington Chp Ltd hold retention?

Winnington Chp Ltd declares no retention clauses in its construction contracts in this filing. Your subcontract governs; if it holds retention, the contract terms decide when it is released.

Can I charge Winnington Chp Ltd interest on a late invoice?

Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.