Average time to pay
38 days
Register median: 31 days
Supplier payment record · 00465899
Reported period: –
View the government filing38 days
Register median: 31 days
76%
Register median: 14%
0 to 50 days
Declared in this filing
These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.
Already waiting for payment?
Use your amount and dates to estimate late-payment interest and fixed compensation.
16 filings
Late payments up 2 percentage pointsCompared with the previous filing
| Period ending | Days to pay | Paid late | Within 30 days | Over 60 days |
|---|---|---|---|---|
| 31 March 2026 | 38 | 76% | 28% | 1% |
| 30 September 2025 | 38 | 74% | 26% | 2% |
| 31 March 2025 | 38 | 74% | 26% | 1% |
| 30 September 2024 | 36 | 73% | 30% | 1% |
| 31 March 2024 | 37 | 75% | 30% | 1% |
| 30 September 2023 | 38 | 79% | 31% | 1% |
Standard payment terms are 50 days from date of invoice, but exceptions are Wheat suppliers (28 days from date of invoice), Maize suppliers (0 days / due immediately) and Wheat boats (0 days / due immediately).
As a business we will always try and pay to our agreed supplier terms, but we only do a non-wheat payment run once a week which invariably will result in most of our payments appearing late, even if only by a few days. If you take this weekly payment run practice into account and allow 7 days tolerance on the due date, our non-payment % reduces to <10%.
We are a food manufacturer and are not in the business of construction so our construction contracts are reviewed on a case by case basis as they are not regularly occurring contracts. There are no set or standard treatment for retentions.
Whitworth Bros.Ltd reported an average of 38 days to pay an invoice for 1 October 2025 to 31 March 2026, with 28% of invoices paid within 30 days and 1% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
By its own filing, 76% of Whitworth Bros.Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 2 points on its previous filing (74% for the period to 30 September 2025).
Yes. Whitworth Bros.Ltd declares retention clauses in its construction contracts, though not in all of them. The filing's own wording is quoted above.
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.