Average time to pay
38 days
Register median: 31 days
Supplier payment record · 03147949
Reported period: –
View the government filing38 days
Register median: 31 days
58%
Register median: 14%
40 days
Declared in this filing
These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.
Already waiting for payment?
Use your amount and dates to estimate late-payment interest and fixed compensation.
17 filings
Late payments down 9 percentage pointsCompared with the previous filing
| Period ending | Days to pay | Paid late | Within 30 days | Over 60 days |
|---|---|---|---|---|
| 30 June 2026 | 38 | 58% | 40% | 8% |
| 31 December 2025 | 37 | 67% | 37% | 6% |
| 30 June 2025 | 36 | 0% | 35% | 5% |
| 31 December 2024 | 38 | 69% | 28% | 4% |
| 30 June 2024 | 40 | 69% | 38% | 4% |
| 31 December 2023 | 38 | 62% | 34% | 5% |
The standard payment terms agreed with most suppliers are 40 days. The company operates a weekly supplier payment run by BACS, which will include all processed invoices due when the payment run is compiled (barring those on hold or in dispute). There are some notable exceptions to these terms: - Franchise fees for many of the brands operated by the company are paid monthly on a date set by the franchisor. - Direct Debits are utilised where deemed required and fit for purpose.
Depending on the risk profile of construction work.
Welcome Break Group Ltd reported an average of 38 days to pay an invoice for 1 January 2026 to 30 June 2026, with 40% of invoices paid within 30 days and 8% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
By its own filing, 58% of Welcome Break Group Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is down 9 points on its previous filing (67% for the period to 31 December 2025).
Yes. Welcome Break Group Ltd declares retention clauses in its construction contracts, though not in all of them. The filing's own wording is quoted above.
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.