Supplier payment record · 02539870

Watkin Jones & Son Ltd

Reported period: –

View the government filing

Average time to pay

46 days

Register median: 31 days

Invoices paid late

10%

Register median: 14%

Standard payment terms

60 to 65 days

Declared in this filing

These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.

Already waiting for payment?

Check your own invoice.

Use your amount and dates to estimate late-payment interest and fixed compensation.

17 filings

How payments have changed

Late payments unchangedCompared with the previous filing

Watkin Jones & Son Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H1 180%25%50%0d45d90dH1 18H1 19H1 20H1 21H1 22H1 23H1 24H1 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
View 6 recent filings
Recent payment filings by Watkin Jones & Son Ltd
Period endingDays to payPaid lateWithin 30 daysOver 60 days
31 March 20264610%32%15%
30 September 20255610%26%17%
31 March 20255112%26%16%
30 September 20245611%28%17%
31 March 20245113%25%17%
30 September 2023499%23%14%

More from the filing

Payment terms and invoice breakdown
Standard payment terms
60 to 65 days
Maximum contractual period
65 days
Paid within 30 days
32%
Paid in 31–60 days
53%
Paid after 60 days
15%
Not paid because of a dispute
2%

The company’s own wording

The standard terms for suppliers are payment at the end of the month following date of invoice. The standard terms for sub-contractors are 60 days from receipt of invoice.
RetentionDeclared
Standard retention rate
5%
In all construction contracts
Yes
Same terms as their own client
No

Common questions

How long does Watkin Jones & Son Ltd take to pay its suppliers?

Watkin Jones & Son Ltd reported an average of 46 days to pay an invoice for 1 October 2025 to 31 March 2026, with 32% of invoices paid within 30 days and 15% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.

Does Watkin Jones & Son Ltd pay late?

By its own filing, 10% of Watkin Jones & Son Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is unchanged on its previous filing (10% for the period to 30 September 2025).

Does Watkin Jones & Son Ltd hold retention?

Yes. Watkin Jones & Son Ltd declares retention clauses in its construction contracts at a standard rate of 5%, in all of them. The filing's own wording is quoted above.

Can I charge Watkin Jones & Son Ltd interest on a late invoice?

Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.