Skip to content
fulcrum
Contact
filing to 30 June 2026

// payment practices, as filed · company 01141788

Wates Property Services Ltd: how it pays its suppliers, from its own filing

Wates Property Services Ltd reports paying its suppliers in an average of 31 days, with 17% of invoices paid later than the agreed terms, for the period 1 January 2026 to 30 June 2026. Across the 1,496 companies that report on construction contracts, the median is 31 days and 14% late. Every figure below is the company’s own, approved by a director and published on the government register; this page reproduces it and says what it means for a subcontractor.

31 days

Average days to pay

longer than 47% of the 1,496 filers; median 31 days

17%

Paid later than agreed

a higher share than 56% of filers; median 14%

68%

Paid within 30 days

4% took longer than 60 days

The terms it declares

Standard payment terms
30 days
Maximum contractual period
61 days
Paid in 31 to 60 days
28%
Paid after 60 days
4%
Not paid because of a dispute
0%
Filed on
29 July 2026

Their standard terms, in their words

30 days

Every filing since Jun 2018

Wates Property Services Ltd has filed 17 times. The share paid late is down 1 points on the previous filing, and the average days to pay unchanged. The first filing, for the period to 30 June 2018, reported 43 days and 61% late.

Wates Property Services Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H1 180%37.5%75%0d30d60dH1 18H1 19H1 20H1 21H1 22H1 23H1 24H1 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
The last six filings by Wates Property Services Ltd
Period toDays to payPaid lateWithin 30 daysOver 60 days
30 June 20263117%68%4%
31 December 20253118%67%4%
30 June 20252311%85%2%
31 December 20242512%79%4%
30 June 20243622%51%7%
31 December 20233414%48%2%

Retention

Retention clauses in construction contracts
yes
Standard retention rate
5%
In all construction contracts
no
Same terms they receive from their own client
no
When they apply retention
The property maintenance and refurbishment works we deliver vary significantly in scale and complexity. For routine maintenance and facilities management contracts, retention clauses are not typically applied to our supply chain. However, for larger and more complex planned maintenance and project works, retention provisions are generally included within subcontract agreements. These retentions are held to ensure the satisfactory completion of works, including snagging, provision of required documentation and certifications, and the rectification of defects. In some circumstances, we may …

What this means if you are pricing work for them

The share paid later than agreed is the number to read first, because a short term makes an invoice late sooner and a long one hides lateness inside the term. Wates Property Services Ltd is above the median on that measure, so build the delay into your cash flow before you sign. The average days to pay sits at the median.

A worked example on a 30-day term: an invoice of £10,000.00 paid on this company’s average, 1 day after the final date, carries £3.22 of statutory interest at 11.75% plus the fixed sum, £103.22 in all, which the law lets you add without a clause. Run your own figures.

Against the official benchmark: the Department for Business and Trade’s statistics for 2025, published 14 July 2026, put large construction businesses at 33 days to pay with 14% of invoices late by number (13% by value), and all large businesses at 32 days and 15% late. Wates Property Services Ltd is at or inside the sector figure on days. Its late share is above the sector figure.

What the register does not show: it is self-reported, large companies only, and the filing covers the whole company, not your contract. Read it alongside the notice rules that decide what you are actually owed, and keep your own dates.

Questions subcontractors ask about Wates Property Services Ltd

How long does Wates Property Services Ltd take to pay its suppliers?
Wates Property Services Ltd reported an average of 31 days to pay an invoice for 1 January 2026 to 30 June 2026, with 68% of invoices paid within 30 days and 4% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
Does Wates Property Services Ltd pay late?
By its own filing, 17% of Wates Property Services Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is down 1 points on its previous filing (18% for the period to 31 December 2025).
Does Wates Property Services Ltd hold retention?
Yes. Wates Property Services Ltd declares retention clauses in its construction contracts at a standard rate of 5%, though not in all of them. The filing's own wording is quoted above.
Can I charge Wates Property Services Ltd interest on a late invoice?
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.

Source: the company’s own report on the government’s payment practices service, report 114804, made under the Reporting on Payment Practices and Performance Regulations 2017 and reproduced under the Open Government Licence v3.0. Register copy taken 2 October 2026; comparisons are against the latest filing of each of the 1,496 companies declaring construction contracts. Figures are as filed, not judged. Not legal advice.