Supplier payment record · 00638559

Volkerhighways Ltd

Reported period: –

View the government filing

Average time to pay

29 days

Register median: 31 days

Invoices paid late

13%

Register median: 14%

Standard payment terms

14 to 60 days

Declared in this filing

These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.

Already waiting for payment?

Check your own invoice.

Use your amount and dates to estimate late-payment interest and fixed compensation.

17 filings

How payments have changed

Late payments down 4 percentage pointsCompared with the previous filing

Volkerhighways Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H1 180%25%50%0d30d60dH1 18H1 19H1 20H1 21H1 22H1 23H1 24H1 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
View 6 recent filings
Recent payment filings by Volkerhighways Ltd
Period endingDays to payPaid lateWithin 30 daysOver 60 days
30 June 20262913%73%5%
31 December 20252917%69%5%
30 June 20252716%72%4%
31 December 20242715%72%3%
30 June 20242623%74%5%
31 December 20233533%57%13%

More from the filing

Payment terms and invoice breakdown
Standard payment terms
14 to 60 days
Maximum contractual period
60 days
Paid within 30 days
73%
Paid in 31–60 days
22%
Paid after 60 days
5%
Not paid because of a dispute
13%

The company’s own wording

VolkerHighways Limited agree payment terms with suppliers and subcontractors as part of negotiating and agreeing their contracts. Our standard payment terms for suppliers and subcontractors with less than 50 employees is 30 days after the date of invoice. For other materials and plant suppliers our standard payment terms are 60 days after the date of invoice. Other payment terms will be agreed with our suppliers and subcontractors on an individual basis.

The company’s explanation

VolkerHighways Limited is committed to supporting the local community wherever we work and endeavour to engage with Small to Medium Enterprises (SMEs), community sector organisations and a diverse range of enterprises in our supply chain. We ensure our procurement processes are transparent, straightforward, and open and we are committed to paying our SME supply chain promptly in recognition of their specific challenge around cash flow, and encourage our supply chain to adopt supporting practices. In order for invoices to be paid on a timely basis, all invoices must be received by our Volker…
RetentionDeclared
Standard retention rate
Not stated
In all construction contracts
No
Same terms as their own client
Yes
We may withhold retentions from payments to subcontractors depending on the type, size and risk profile associated with the subcontract works.
For projects where our clients deduct retentions from payments, we aim to use consistent retention clauses with our supply chain.

Common questions

How long does Volkerhighways Ltd take to pay its suppliers?

Volkerhighways Ltd reported an average of 29 days to pay an invoice for 1 January 2026 to 30 June 2026, with 73% of invoices paid within 30 days and 5% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.

Does Volkerhighways Ltd pay late?

By its own filing, 13% of Volkerhighways Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is down 4 points on its previous filing (17% for the period to 31 December 2025).

Does Volkerhighways Ltd hold retention?

Yes. Volkerhighways Ltd declares retention clauses in its construction contracts, though not in all of them. The filing's own wording is quoted above.

Can I charge Volkerhighways Ltd interest on a late invoice?

Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.