Average time to pay
60 days
Register median: 31 days
Supplier payment record · 02366661
Reported period: –
View the government filing60 days
Register median: 31 days
14%
Register median: 14%
1 to 91 days
Declared in this filing
These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.
Already waiting for payment?
Use your amount and dates to estimate late-payment interest and fixed compensation.
16 filings
Late payments unchangedCompared with the previous filing
| Period ending | Days to pay | Paid late | Within 30 days | Over 60 days |
|---|---|---|---|---|
| 31 March 2026 | 60 | 14% | 25% | 43% |
| 30 September 2025 | 63 | 14% | 25% | 42% |
| 31 March 2025 | 61 | 16% | 25% | 43% |
| 30 September 2024 | 64 | 17% | 22% | 53% |
| 31 March 2024 | 58 | 28% | 25% | 44% |
| 30 September 2023 | 59 | 18% | 23% | 51% |
Unless otherwise agreed, our standard payment terms are 60 end of month. This means payment is due at the last day of the second month following receipt of a correctly presented compliant invoice. e.g. valid invoice received on 1st July would be due for payment on 30th September (91 days), valid invoice received on 31st July would be due for payment on 30th September (61 days)
We operate a weekly BACS and cheque run which includes invoices due up until the Sunday of that week. Of the 14% of invoices due but not paid within agreed terms referred to in the Payment Statistics section above, 65% are overdue by 1-5 days. This is attributed to our weekly payment timetable. The remaining invoices not paid within the agreed terms are for invoices that are being queried or are in dispute.
For this submission period, only a select minority of construction contracts have retention clauses, these are focused around some of our capital projects. We currently have 2 retention options used in these contracts: 1. An Initial payment of 45 days after invoice with a 5% retention withheld. 2. An Initial payment of 45 days after invoice with 3% retention withheld.
Thames Water Utilities Ltd reported an average of 60 days to pay an invoice for 1 October 2025 to 31 March 2026, with 25% of invoices paid within 30 days and 43% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
By its own filing, 14% of Thames Water Utilities Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is unchanged on its previous filing (14% for the period to 30 September 2025).
Yes. Thames Water Utilities Ltd declares retention clauses in its construction contracts, though not in all of them. The filing's own wording is quoted above.
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.