Supplier payment record · 07736448

Tenterden Schools Trust

Reported period: –

View the government filing

Average time to pay

20 days

Register median: 31 days

Invoices paid late

16%

Register median: 14%

Standard payment terms

30 days

Declared in this filing

These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.

Already waiting for payment?

Check your own invoice.

Use your amount and dates to estimate late-payment interest and fixed compensation.

4 filings

How payments have changed

Late payments up 1 percentage pointsCompared with the previous filing

Tenterden Schools Trust: share of invoices paid late (bars) and average days to pay (line), every filing since H1 250%25%50%0d30d60dH1 25H2 25H1 26H2 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
View 4 recent filings
Recent payment filings by Tenterden Schools Trust
Period endingDays to payPaid lateWithin 30 daysOver 60 days
31 August 20262016%80%1%
28 February 20261915%85%1%
31 August 20251915%85%1%
28 February 20252429%71%3%

More from the filing

Payment terms and invoice breakdown
Standard payment terms
30 days
Maximum contractual period
30 days
Paid within 30 days
80%
Paid in 31–60 days
19%
Paid after 60 days
1%
Not paid because of a dispute
0%

The company’s own wording

The standard term is 30 days for all invoices
RetentionDeclared
Standard retention rate
5%
In all construction contracts
No
Same terms as their own client
No
Construction contracts funded via CIF funding contain a retention clause as standard practice.

Common questions

How long does Tenterden Schools Trust take to pay its suppliers?

Tenterden Schools Trust reported an average of 20 days to pay an invoice for 1 March 2026 to 31 August 2026, with 80% of invoices paid within 30 days and 1% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.

Does Tenterden Schools Trust pay late?

By its own filing, 16% of Tenterden Schools Trust's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 1 points on its previous filing (15% for the period to 28 February 2026).

Does Tenterden Schools Trust hold retention?

Yes. Tenterden Schools Trust declares retention clauses in its construction contracts at a standard rate of 5%, though not in all of them. The filing's own wording is quoted above.

Can I charge Tenterden Schools Trust interest on a late invoice?

Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.