Skip to content
fulcrum
Contact

Supplier payment record · 03709861

Story Contracting Ltd

Reported period: –

View the government filing

Average time to pay

30 days

Register median: 31 days

Invoices paid late

22%

Register median: 14%

Standard payment terms

14 to 62 days

Declared in this filing

These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.

Already waiting for payment?

Check your own invoice.

Use your amount and dates to estimate late-payment interest and fixed compensation.

16 filings

How payments have changed

Late payments up 3 percentage pointsCompared with the previous filing

Story Contracting Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H2 180%12.5%25%0d30d60dH2 18H2 19H2 20H2 21H2 22H2 23H2 24H2 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
View 6 recent filings
Recent payment filings by Story Contracting Ltd
Period endingDays to payPaid lateWithin 30 daysOver 60 days
31 March 20263022%58%5%
30 September 20253219%57%4%
31 March 20253113%60%5%
30 September 20244114%62%6%
31 March 20243218%61%7%
30 September 20233913%43%13%

More from the filing

Payment terms and invoice breakdown
Standard payment terms
14 to 62 days
Maximum contractual period
60 days
Paid within 30 days
58%
Paid in 31–60 days
37%
Paid after 60 days
5%
Not paid because of a dispute
2%

The company’s own wording

Default terms are end of month following invoice date
RetentionDeclared
Standard retention rate
Not stated
In all construction contracts
No
Same terms as their own client
Yes
Mainly the civil contracts use retentions
Not always applied and generally match 5% applied to us

Common questions

How long does Story Contracting Ltd take to pay its suppliers?

Story Contracting Ltd reported an average of 30 days to pay an invoice for 1 October 2025 to 31 March 2026, with 58% of invoices paid within 30 days and 5% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.

Does Story Contracting Ltd pay late?

By its own filing, 22% of Story Contracting Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 3 points on its previous filing (19% for the period to 30 September 2025).

Does Story Contracting Ltd hold retention?

Yes. Story Contracting Ltd declares retention clauses in its construction contracts, though not in all of them. The filing's own wording is quoted above.

Can I charge Story Contracting Ltd interest on a late invoice?

Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.