Skip to content
fulcrum
Contact

Supplier payment record · 02366937

Sp Manweb PLC

Reported period: –

View the government filing

Average time to pay

30 days

Register median: 31 days

Invoices paid late

10%

Register median: 14%

Standard payment terms

30 to 60 days

Declared in this filing

These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.

Already waiting for payment?

Check your own invoice.

Use your amount and dates to estimate late-payment interest and fixed compensation.

17 filings

How payments have changed

Late payments down 2 percentage pointsCompared with the previous filing

Sp Manweb PLC: share of invoices paid late (bars) and average days to pay (line), every filing since H1 180%25%50%0d30d60dH1 18H1 19H1 20H1 21H1 22H1 23H1 24H1 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
View 6 recent filings
Recent payment filings by Sp Manweb PLC
Period endingDays to payPaid lateWithin 30 daysOver 60 days
30 June 20263010%87%2%
31 December 20253112%94%2%
30 June 20253120%79%2%
31 December 20242812%94%3%
30 June 20242912%86%2%
31 December 20232714%95%2%

More from the filing

Payment terms and invoice breakdown
Standard payment terms
30 to 60 days
Maximum contractual period
60 days
Paid within 30 days
87%
Paid in 31–60 days
11%
Paid after 60 days
2%
Not paid because of a dispute
0%

The company’s own wording

30 days from invoice date
RetentionNone declared

No retention clauses were declared in this filing.

Common questions

How long does Sp Manweb PLC take to pay its suppliers?

Sp Manweb PLC reported an average of 30 days to pay an invoice for 1 January 2026 to 30 June 2026, with 87% of invoices paid within 30 days and 2% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.

Does Sp Manweb PLC pay late?

By its own filing, 10% of Sp Manweb PLC's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is down 2 points on its previous filing (12% for the period to 31 December 2025).

Does Sp Manweb PLC hold retention?

Sp Manweb PLC declares no retention clauses in its construction contracts in this filing. Your subcontract governs; if it holds retention, the contract terms decide when it is released.

Can I charge Sp Manweb PLC interest on a late invoice?

Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.