Average time to pay
30 days
Register median: 31 days
Supplier payment record · 02366665
Reported period: –
View the government filing30 days
Register median: 31 days
28%
Register median: 14%
14 to 31 days
Declared in this filing
These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.
Already waiting for payment?
Use your amount and dates to estimate late-payment interest and fixed compensation.
15 filings
Late payments down 4 percentage pointsCompared with the previous filing
| Period ending | Days to pay | Paid late | Within 30 days | Over 60 days |
|---|---|---|---|---|
| 30 September 2025 | 30 | 28% | 61% | 7% |
| 31 March 2025 | 27 | 32% | 62% | 4% |
| 30 September 2024 | 33 | 33% | 49% | 4% |
| 31 March 2024 | 31 | 36% | 64% | 3% |
| 30 September 2023 | 30 | 38% | 49% | 4% |
| 31 March 2023 | 31 | 21% | 55% | 4% |
30 days after the end of the month of receipt by the Company of a proper and undisputed invoice.
A valid invoice reflects: • registered and approved supplier • purchase order number • includes the necessary details of goods/services, date and financial detail and sent either electronically to invoices@southwestwater.co.uk or by post. Whilst South West Water is not a member of the prompt payment code, we do adopt the principles of the code including: 1. paying suppliers on time – with average payment days which is below our standard terms and lower than 30 days 2. Clear guidance to suppliers – our terms and conditions are included within our purchase orders and on our website. 3. …
No retention clauses were declared in this filing.
South West Water Ltd reported an average of 30 days to pay an invoice for 1 April 2025 to 30 September 2025, with 61% of invoices paid within 30 days and 7% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
By its own filing, 28% of South West Water Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is down 4 points on its previous filing (32% for the period to 31 March 2025).
South West Water Ltd declares no retention clauses in its construction contracts in this filing. Your subcontract governs; if it holds retention, the contract terms decide when it is released.
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.