Supplier payment record · 00191408

Skanska Construction UK Ltd

Reported period: –

View the government filing

Average time to pay

29 days

Register median: 31 days

Invoices paid late

8%

Register median: 14%

Standard payment terms

30 days

Declared in this filing

These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.

Already waiting for payment?

Check your own invoice.

Use your amount and dates to estimate late-payment interest and fixed compensation.

17 filings

How payments have changed

Late payments down 3 percentage pointsCompared with the previous filing

Skanska Construction UK Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H1 180%25%50%0d30d60dH1 18H1 19H1 20H1 21H1 22H1 23H1 24H1 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
View 6 recent filings
Recent payment filings by Skanska Construction UK Ltd
Period endingDays to payPaid lateWithin 30 daysOver 60 days
30 June 2026298%69%2%
31 December 20252811%71%2%
30 June 2025288%70%2%
31 December 20243012%65%4%
30 June 2024309%67%4%
31 December 20233413%63%8%

More from the filing

Payment terms and invoice breakdown
Standard payment terms
30 days
Maximum contractual period
30 days
Paid within 30 days
69%
Paid in 31–60 days
29%
Paid after 60 days
2%
Not paid because of a dispute
0%

The company’s own wording

Skanska has a standard payment term of 30 days nett following the date the invoice/application was created in the system.

The company’s explanation

Payment performance for companies with less than 50 employees: 0-30 days: 85% 31-60 days: 13% 61+ days: 2%
RetentionDeclared
Standard retention rate
Not stated
In all construction contracts
No
Same terms as their own client
Yes
We do not have a standard retention clause in our sub-contracts; our most frequent clause used is 3%. In general, we would only include this clause when our customer is themselves using a retention clause in our main contract.
We do not have a standard retention clause in our sub-contracts; our most frequent clause used is 3%. In general, we would only include this clause when our customer is themselves using a retention clause in our main contract.

Common questions

How long does Skanska Construction UK Ltd take to pay its suppliers?

Skanska Construction UK Ltd reported an average of 29 days to pay an invoice for 1 January 2026 to 30 June 2026, with 69% of invoices paid within 30 days and 2% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.

Does Skanska Construction UK Ltd pay late?

By its own filing, 8% of Skanska Construction UK Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is down 3 points on its previous filing (11% for the period to 31 December 2025).

Does Skanska Construction UK Ltd hold retention?

Yes. Skanska Construction UK Ltd declares retention clauses in its construction contracts, though not in all of them. The filing's own wording is quoted above.

Can I charge Skanska Construction UK Ltd interest on a late invoice?

Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.