Average time to pay
70 days
Register median: 31 days
Supplier payment record · 00631825
Reported period: –
View the government filing70 days
Register median: 31 days
19%
Register median: 14%
14 to 180 days
Declared in this filing
These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.
Already waiting for payment?
Use your amount and dates to estimate late-payment interest and fixed compensation.
17 filings
Late payments down 3 percentage pointsCompared with the previous filing
| Period ending | Days to pay | Paid late | Within 30 days | Over 60 days |
|---|---|---|---|---|
| 31 March 2026 | 70 | 19% | 12% | 32% |
| 30 September 2025 | 55 | 22% | 29% | 48% |
| 31 March 2025 | 53 | 26% | 31% | 49% |
| 30 September 2024 | 58 | 23% | 22% | 56% |
| 31 March 2024 | 61 | 26% | 21% | 59% |
| 30 September 2023 | 60 | 27% | 23% | 56% |
The payment terms are assigned by the Business units on a case by case basis:- Payment terms usage : 9% of the transactions are on Intercompany Clearing payment terms and are paid immediately in the month following the receipt of the invoice. Please note Intercompany clearing terms are available to Siemens Energy companies only and payment method for such terms results in clearing of such transactions without any transmission of money external to Siemens Energy cash pool. 3rd party payments terms usage is as follows 60 days 52%, 90 days 18%, 30 days 12%, 45 days 3%, 14 Days 2%, 0 days 2%, 12…
Early settlement discounts are applied as agreed with the suppliers and range from 1% to 3% based upon the timing of payments. During the reporting less than 1% of the overall transactions showed pre-agreed discounts with the suppliers.
No retention clauses were declared in this filing.
Siemens Energy Ltd reported an average of 70 days to pay an invoice for 1 October 2025 to 31 March 2026, with 12% of invoices paid within 30 days and 32% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
By its own filing, 19% of Siemens Energy Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is down 3 points on its previous filing (22% for the period to 30 September 2025).
Siemens Energy Ltd declares no retention clauses in its construction contracts in this filing. Your subcontract governs; if it holds retention, the contract terms decide when it is released.
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.