Supplier payment record · 04864216

Sheffield Forgemasters Engineering Ltd

Reported period: –

View the government filing

Average time to pay

43 days

Register median: 31 days

Invoices paid late

15%

Register median: 14%

Standard payment terms

15 days

Declared in this filing

These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.

Already waiting for payment?

Check your own invoice.

Use your amount and dates to estimate late-payment interest and fixed compensation.

17 filings

How payments have changed

Late payments up 3 percentage pointsCompared with the previous filing

Sheffield Forgemasters Engineering Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H1 180%37.5%75%0d45d90dH1 18H1 19H1 20H1 21H1 22H1 23H1 24H1 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
View 6 recent filings
Recent payment filings by Sheffield Forgemasters Engineering Ltd
Period endingDays to payPaid lateWithin 30 daysOver 60 days
31 March 20264315%35%28%
30 September 20254012%39%21%
31 March 2025458%30%28%
30 September 2024508%27%30%
31 March 2024489%34%27%
31 December 20235218%25%30%

More from the filing

Payment terms and invoice breakdown
Standard payment terms
15 days
Maximum contractual period
90 days
Paid within 30 days
35%
Paid in 31–60 days
37%
Paid after 60 days
28%
Not paid because of a dispute
0%

The company’s own wording

Typically 30 or 60 days depending on what is agreed with supplier. Larger value suppliers (particularly Recapitalisation project suppliers, such as Vinci Construction, McLaughlin & Harvey) have 28 day terms which drives the figure paid within 30 days.
RetentionDeclared
Standard retention rate
Not stated
In all construction contracts
No
Same terms as their own client
No
Depending on nature of supplier/contractor.

Common questions

How long does Sheffield Forgemasters Engineering Ltd take to pay its suppliers?

Sheffield Forgemasters Engineering Ltd reported an average of 43 days to pay an invoice for 1 October 2025 to 31 March 2026, with 35% of invoices paid within 30 days and 28% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.

Does Sheffield Forgemasters Engineering Ltd pay late?

By its own filing, 15% of Sheffield Forgemasters Engineering Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 3 points on its previous filing (12% for the period to 30 September 2025).

Does Sheffield Forgemasters Engineering Ltd hold retention?

Yes. Sheffield Forgemasters Engineering Ltd declares retention clauses in its construction contracts, though not in all of them. The filing's own wording is quoted above.

Can I charge Sheffield Forgemasters Engineering Ltd interest on a late invoice?

Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.