Severn Trent Water Ltd: how it pays its suppliers, from its own filing

Severn Trent Water Ltd reports paying its suppliers in an average of 40 days, with 10% of invoices paid later than the agreed terms, for the period 1 October 2025 to 31 March 2026. Across the 1,496 companies that report on construction contracts, the median is 31 days and 14% late. Every figure below is the company’s own, approved by a director and published on the government register; this page reproduces it and says what it means for a subcontractor.

40 days

Average days to pay

longer than 72% of the 1,496 filers; median 31 days

10%

Paid later than agreed

a higher share than 36% of filers; median 14%

72%

Paid within 30 days

8% took longer than 60 days

The terms it declares

Standard payment terms
15 to 60 days
Maximum contractual period
90 days
Paid in 31 to 60 days
20%
Paid after 60 days
8%
Not paid because of a dispute
0%
Filed on
30 April 2026

Their standard terms, in their words

Severn Trent Water’s standard payment term for new contracts is 60 days (or 30 days for businesses with less than 50 employees); this applies across all contracts raised and would be agreed with suppliers prior to the commencement of the trading activity. On occasion, authorisation may be granted to reduce the payment terms below 60 days if there is commercial requirement/benefit in doing so. Such a change requires approval from the Commercial team. We would not attempt to impose payment terms longer than 60 days on any of our suppliers, nor do we use early settlement discounts as part of c…

Their explanation

N/A

Every filing since Sep 2018

Severn Trent Water Ltd has filed 16 times. The share paid late is up 3 points on the previous filing, and the average days to pay up 3 days. The first filing, for the period to 30 September 2018, reported 33 days and 5% late.

Severn Trent Water Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H2 180%12.5%25%0d30d60dH2 18H2 19H2 20H2 21H2 22H2 23H2 24H2 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
The last six filings by Severn Trent Water Ltd
Period toDays to payPaid lateWithin 30 daysOver 60 days
31 March 20264010%72%8%
30 September 2025377%76%4%
31 March 2025344%82%3%
30 September 2024334%84%2%
31 March 2024334%85%3%
30 September 2023324%85%2%

Retention

Retention clauses in construction contracts
yes
Standard retention rate
not stated
In all construction contracts
no
Same terms they receive from their own client
no
When they apply retention
Severn Trent Water (STW) enters into large numbers of qualifying construction contracts, mainly as an employer. It utilises a series of different terms and conditions dependent upon the complexity, value and nature of what is being constructed. STW uses, amongst other terms, NEC and JCT based contracts. Some of STW’s qualifying construction contracts do contain retention clauses, either as secondary options, such as the NEC X16, or as standalone provisions to drive supplier behaviours, such as in relation to timely provision of programmes and/or warranties. When considering whether to inclu…

What this means if you are pricing work for them

The share paid later than agreed is the number to read first, because a short term makes an invoice late sooner and a long one hides lateness inside the term. Severn Trent Water Ltd is at or below the median on that measure. The average days to pay sits over the median.

A worked example on a 30-day term: an invoice of £10,000.00 paid on this company’s average, 10 days after the final date, carries £32.19 of statutory interest at 11.75% plus the fixed sum, £132.19 in all, which the law lets you add without a clause. Run your own figures.

Against the official benchmark: the Department for Business and Trade’s statistics for 2025, published 14 July 2026, put large construction businesses at 33 days to pay with 14% of invoices late by number (13% by value), and all large businesses at 32 days and 15% late. Severn Trent Water Ltd is slower than the sector figure. Its late share is at or below the sector figure.

What the register does not show: it is self-reported, large companies only, and the filing covers the whole company, not your contract. Read it alongside the notice rules that decide what you are actually owed, and keep your own dates.

Questions subcontractors ask about Severn Trent Water Ltd

How long does Severn Trent Water Ltd take to pay its suppliers?
Severn Trent Water Ltd reported an average of 40 days to pay an invoice for 1 October 2025 to 31 March 2026, with 72% of invoices paid within 30 days and 8% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
Does Severn Trent Water Ltd pay late?
By its own filing, 10% of Severn Trent Water Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 3 points on its previous filing (7% for the period to 30 September 2025).
Does Severn Trent Water Ltd hold retention?
Yes. Severn Trent Water Ltd declares retention clauses in its construction contracts, though not in all of them. The filing's own wording is quoted above.
Can I charge Severn Trent Water Ltd interest on a late invoice?
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.

Source: the company’s own report on the government’s payment practices service, report 111598, made under the Reporting on Payment Practices and Performance Regulations 2017 and reproduced under the Open Government Licence v3.0. Register copy taken 2 October 2026; comparisons are against the latest filing of each of the 1,496 companies declaring construction contracts. Figures are as filed, not judged. Not legal advice.