Supplier payment record · 00364651

Sc Johnson Professional Ltd

Reported period: –

View the government filing

Average time to pay

52 days

Register median: 31 days

Invoices paid late

24%

Register median: 14%

Standard payment terms

0 to 110 days

Declared in this filing

These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.

Already waiting for payment?

Check your own invoice.

Use your amount and dates to estimate late-payment interest and fixed compensation.

18 filings

How payments have changed

Late payments up 10 percentage pointsCompared with the previous filing

Sc Johnson Professional Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H2 170%37.5%75%0d30d60dH2 17H2 18H2 19H2 20H2 21H2 22H2 23H2 24H2 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
View 6 recent filings
Recent payment filings by Sc Johnson Professional Ltd
Period endingDays to payPaid lateWithin 30 daysOver 60 days
30 June 20265224%34%30%
31 December 20254714%36%24%
30 June 20254516%37%20%
31 December 20244717%30%32%
30 June 20243322%25%33%
31 December 20233523%24%34%

More from the filing

Payment terms and invoice breakdown
Standard payment terms
0 to 110 days
Maximum contractual period
110 days
Paid within 30 days
34%
Paid in 31–60 days
36%
Paid after 60 days
30%
Not paid because of a dispute
0%

The company’s own wording

The company operates on 60 days from invoice standard payment terms with suppliers but each contract can potentially be negotiated separately. The most common transacted payment terms are 60 days’ from invoice, these terms account for 31% of transactions within the period. All supplier’s payment terms have remained consistent throughout the reporting period. With regards to different types of qualifying contracts, raw material suppliers and services most commonly have the agreed terms of 60 days from invoice. The maximum agreed terms in use are 110 days from invoice date. The extended paymen…

The company’s explanation

Not Applicable
RetentionNone declared

No retention clauses were declared in this filing.

Common questions

How long does Sc Johnson Professional Ltd take to pay its suppliers?

Sc Johnson Professional Ltd reported an average of 52 days to pay an invoice for 1 January 2026 to 30 June 2026, with 34% of invoices paid within 30 days and 30% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.

Does Sc Johnson Professional Ltd pay late?

By its own filing, 24% of Sc Johnson Professional Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 10 points on its previous filing (14% for the period to 31 December 2025).

Does Sc Johnson Professional Ltd hold retention?

Sc Johnson Professional Ltd declares no retention clauses in its construction contracts in this filing. Your subcontract governs; if it holds retention, the contract terms decide when it is released.

Can I charge Sc Johnson Professional Ltd interest on a late invoice?