Sacyr UK Ltd: how it pays its suppliers, from its own filing

Sacyr UK Ltd reports paying its suppliers in an average of 37 days, with 24% of invoices paid later than the agreed terms, for the period 1 January 2026 to 30 June 2026. Across the 1,496 companies that report on construction contracts, the median is 31 days and 14% late. Every figure below is the company’s own, approved by a director and published on the government register; this page reproduces it and says what it means for a subcontractor.

37 days

Average days to pay

longer than 66% of the 1,496 filers; median 31 days

24%

Paid later than agreed

a higher share than 69% of filers; median 14%

59%

Paid within 30 days

6% took longer than 60 days

The terms it declares

Standard payment terms
30 days
Maximum contractual period
60 days
Paid in 31 to 60 days
35%
Paid after 60 days
6%
Not paid because of a dispute
9%
Filed on
22 September 2026

Their standard terms, in their words

SACYR UK LIMITED does not have standard payment terms. Payment terms are agreed with suppliers as part of contract negotiations. The most frequently used payment terms in the reporting period are 30 days from date of invoice.

Retention

Retention clauses in construction contracts
yes
Standard retention rate
not stated
In all construction contracts
no
Same terms they receive from their own client
yes
On parity with their client
3% Retention.

What this means if you are pricing work for them

The share paid later than agreed is the number to read first, because a short term makes an invoice late sooner and a long one hides lateness inside the term. Sacyr UK Ltd is above the median on that measure, so build the delay into your cash flow before you sign. The average days to pay sits over the median.

A worked example on a 30-day term: an invoice of £10,000.00 paid on this company’s average, 7 days after the final date, carries £22.53 of statutory interest at 11.75% plus the fixed sum, £122.53 in all, which the law lets you add without a clause. Run your own figures.

Against the official benchmark: the Department for Business and Trade’s statistics for 2025, published 14 July 2026, put large construction businesses at 33 days to pay with 14% of invoices late by number (13% by value), and all large businesses at 32 days and 15% late. Sacyr UK Ltd is slower than the sector figure. Its late share is above the sector figure.

What the register does not show: it is self-reported, large companies only, and the filing covers the whole company, not your contract. Read it alongside the notice rules that decide what you are actually owed, and keep your own dates.

Questions subcontractors ask about Sacyr UK Ltd

How long does Sacyr UK Ltd take to pay its suppliers?
Sacyr UK Ltd reported an average of 37 days to pay an invoice for 1 January 2026 to 30 June 2026, with 59% of invoices paid within 30 days and 6% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
Does Sacyr UK Ltd pay late?
By its own filing, 24% of Sacyr UK Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts.
Does Sacyr UK Ltd hold retention?
Yes. Sacyr UK Ltd declares retention clauses in its construction contracts, though not in all of them. The filing's own wording is quoted above.
Can I charge Sacyr UK Ltd interest on a late invoice?
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.

Source: the company’s own report on the government’s payment practices service, report 116930, made under the Reporting on Payment Practices and Performance Regulations 2017 and reproduced under the Open Government Licence v3.0. Register copy taken 2 October 2026; comparisons are against the latest filing of each of the 1,496 companies declaring construction contracts. Figures are as filed, not judged. Not legal advice.