Rockline Industries Ltd: how it pays its suppliers, from its own filing

Rockline Industries Ltd reports paying its suppliers in an average of 35 days, with 37% of invoices paid later than the agreed terms, for the period 1 January 2026 to 30 June 2026. Across the 1,496 companies that report on construction contracts, the median is 31 days and 14% late. Every figure below is the company’s own, approved by a director and published on the government register; this page reproduces it and says what it means for a subcontractor.

35 days

Average days to pay

longer than 59% of the 1,496 filers; median 31 days

37%

Paid later than agreed

a higher share than 86% of filers; median 14%

28%

Paid within 30 days

24% took longer than 60 days

The terms it declares

Standard payment terms
30 to 60 days
Maximum contractual period
90 days
Paid in 31 to 60 days
48%
Paid after 60 days
24%
Not paid because of a dispute
2%
Filed on
31 July 2026

Their standard terms, in their words

END OF MONTH FOLLOWING EOMF

Every filing since Dec 2017

Rockline Industries Ltd has filed 18 times. The share paid late is unchanged on the previous filing, and the average days to pay unchanged. The first filing, for the period to 31 December 2017, reported 40 days and 45% late.

Rockline Industries Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H2 170%25%50%0d30d60dH2 17H2 18H2 19H2 20H2 21H2 22H2 23H2 24H2 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
The last six filings by Rockline Industries Ltd
Period toDays to payPaid lateWithin 30 daysOver 60 days
30 June 20263537%28%24%
31 December 20253537%27%25%
30 June 20253738%33%7%
31 December 20244338%31%12%
30 June 20243941%30%11%
31 December 20233736%32%8%

Retention

Retention clauses in construction contracts
yes
Standard retention rate
5%
In all construction contracts
no
Same terms they receive from their own client
yes
When they apply retention
Larger capital investment projects only
On parity with their client
Not part of construction supply chain. No retention applied to RL.

What this means if you are pricing work for them

The share paid later than agreed is the number to read first, because a short term makes an invoice late sooner and a long one hides lateness inside the term. Rockline Industries Ltd is above the median on that measure, so build the delay into your cash flow before you sign. The average days to pay sits over the median.

A worked example on a 30-day term: an invoice of £10,000.00 paid on this company’s average, 5 days after the final date, carries £16.10 of statutory interest at 11.75% plus the fixed sum, £116.10 in all, which the law lets you add without a clause. Run your own figures.

Against the official benchmark: the Department for Business and Trade’s statistics for 2025, published 14 July 2026, put large construction businesses at 33 days to pay with 14% of invoices late by number (13% by value), and all large businesses at 32 days and 15% late. Rockline Industries Ltd is slower than the sector figure. Its late share is above the sector figure.

What the register does not show: it is self-reported, large companies only, and the filing covers the whole company, not your contract. Read it alongside the notice rules that decide what you are actually owed, and keep your own dates.

Questions subcontractors ask about Rockline Industries Ltd

How long does Rockline Industries Ltd take to pay its suppliers?
Rockline Industries Ltd reported an average of 35 days to pay an invoice for 1 January 2026 to 30 June 2026, with 28% of invoices paid within 30 days and 24% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
Does Rockline Industries Ltd pay late?
By its own filing, 37% of Rockline Industries Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is unchanged on its previous filing (37% for the period to 31 December 2025).
Does Rockline Industries Ltd hold retention?
Yes. Rockline Industries Ltd declares retention clauses in its construction contracts at a standard rate of 5%, though not in all of them. The filing's own wording is quoted above.
Can I charge Rockline Industries Ltd interest on a late invoice?
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.

Source: the company’s own report on the government’s payment practices service, report 115925, made under the Reporting on Payment Practices and Performance Regulations 2017 and reproduced under the Open Government Licence v3.0. Register copy taken 2 October 2026; comparisons are against the latest filing of each of the 1,496 companies declaring construction contracts. Figures are as filed, not judged. Not legal advice.