Skip to content
fulcrum
Contact
filing to 30 June 2026

// payment practices, as filed · company 06426331

Rhodar Industrial Services Ltd: how it pays its suppliers, from its own filing

Rhodar Industrial Services Ltd reports paying its suppliers in an average of 59 days, with 66% of invoices paid later than the agreed terms, for the period 1 January 2026 to 30 June 2026. Across the 1,496 companies that report on construction contracts, the median is 31 days and 14% late. Every figure below is the company’s own, approved by a director and published on the government register; this page reproduces it and says what it means for a subcontractor.

59 days

Average days to pay

longer than 93% of the 1,496 filers; median 31 days

66%

Paid later than agreed

a higher share than 97% of filers; median 14%

33%

Paid within 30 days

27% took longer than 60 days

The terms it declares

Standard payment terms
0 to 60 days
Maximum contractual period
90 days
Paid in 31 to 60 days
40%
Paid after 60 days
27%
Not paid because of a dispute
0%
Filed on
31 July 2026

Their standard terms, in their words

Standard payment terms are 30 days for subcontractors and suppliers unless otherwise agreed

Every filing since Jun 2025

Rhodar Industrial Services Ltd has filed 3 times. The share paid late is up 38 points on the previous filing, and the average days to pay up 6 days. The first filing, for the period to 30 June 2025, reported 50 days and 18% late.

Rhodar Industrial Services Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H1 250%37.5%75%0d30d60dH1 25H2 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
The last six filings by Rhodar Industrial Services Ltd
Period toDays to payPaid lateWithin 30 daysOver 60 days
30 June 20265966%33%27%
31 December 20255328%26%24%
30 June 20255018%26%19%

Retention

Retention clauses in construction contracts
yes
Standard retention rate
not stated
In all construction contracts
no
Same terms they receive from their own client
no
When they apply retention
Some suppliers will want a retention but others won't so it's just based on how the suppliers work, who they are, the level of risk and the value of the works carried out.

What this means if you are pricing work for them

The share paid later than agreed is the number to read first, because a short term makes an invoice late sooner and a long one hides lateness inside the term. Rhodar Industrial Services Ltd is above the median on that measure, so build the delay into your cash flow before you sign. The average days to pay sits over the median.

A worked example on a 30-day term: an invoice of £10,000.00 paid on this company’s average, 29 days after the final date, carries £93.36 of statutory interest at 11.75% plus the fixed sum, £193.36 in all, which the law lets you add without a clause. Run your own figures.

Against the official benchmark: the Department for Business and Trade’s statistics for 2025, published 14 July 2026, put large construction businesses at 33 days to pay with 14% of invoices late by number (13% by value), and all large businesses at 32 days and 15% late. Rhodar Industrial Services Ltd is slower than the sector figure. Its late share is above the sector figure.

What the register does not show: it is self-reported, large companies only, and the filing covers the whole company, not your contract. Read it alongside the notice rules that decide what you are actually owed, and keep your own dates.

Questions subcontractors ask about Rhodar Industrial Services Ltd

How long does Rhodar Industrial Services Ltd take to pay its suppliers?
Rhodar Industrial Services Ltd reported an average of 59 days to pay an invoice for 1 January 2026 to 30 June 2026, with 33% of invoices paid within 30 days and 27% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
Does Rhodar Industrial Services Ltd pay late?
By its own filing, 66% of Rhodar Industrial Services Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 38 points on its previous filing (28% for the period to 31 December 2025).
Does Rhodar Industrial Services Ltd hold retention?
Yes. Rhodar Industrial Services Ltd declares retention clauses in its construction contracts, though not in all of them. The filing's own wording is quoted above.
Can I charge Rhodar Industrial Services Ltd interest on a late invoice?
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.

Source: the company’s own report on the government’s payment practices service, report 115846, made under the Reporting on Payment Practices and Performance Regulations 2017 and reproduced under the Open Government Licence v3.0. Register copy taken 2 October 2026; comparisons are against the latest filing of each of the 1,496 companies declaring construction contracts. Figures are as filed, not judged. Not legal advice.