Skip to content
fulcrum
Contact

Supplier payment record · 04129545

Orsted Burbo (UK) Ltd

Reported period: –

View the government filing

Average time to pay

61 days

Register median: 31 days

Invoices paid late

8%

Register median: 14%

Standard payment terms

30 to 60 days

Declared in this filing

These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.

Already waiting for payment?

Check your own invoice.

Use your amount and dates to estimate late-payment interest and fixed compensation.

3 filings

How payments have changed

Late payments down 1 percentage pointsCompared with the previous filing

Orsted Burbo (UK) Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H1 240%12.5%25%0d45d90dH1 24H2 24H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
View 3 recent filings
Recent payment filings by Orsted Burbo (UK) Ltd
Period endingDays to payPaid lateWithin 30 daysOver 60 days
30 June 2026618%50%3%
31 December 2024249%68%0%
30 June 2024258%64%0%

More from the filing

Payment terms and invoice breakdown
Standard payment terms
30 to 60 days
Maximum contractual period
60 days
Paid within 30 days
50%
Paid in 31–60 days
47%
Paid after 60 days
3%
Not paid because of a dispute
0%

The company’s own wording

Standard contractual length of time for payment of invoices are 30 days from invoice received date. The maximum contractual payment period is 60 days from invoice day.

The company’s explanation

N/A
RetentionNone declared

No retention clauses were declared in this filing.

Common questions

How long does Orsted Burbo (UK) Ltd take to pay its suppliers?

Orsted Burbo (UK) Ltd reported an average of 61 days to pay an invoice for 1 January 2026 to 30 June 2026, with 50% of invoices paid within 30 days and 3% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.

Does Orsted Burbo (UK) Ltd pay late?

By its own filing, 8% of Orsted Burbo (UK) Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is down 1 points on its previous filing (9% for the period to 31 December 2024).

Does Orsted Burbo (UK) Ltd hold retention?

Orsted Burbo (UK) Ltd declares no retention clauses in its construction contracts in this filing. Your subcontract governs; if it holds retention, the contract terms decide when it is released.

Can I charge Orsted Burbo (UK) Ltd interest on a late invoice?

Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.