Skip to content
fulcrum
Contact

Supplier payment record · 02916906

Ocu Utility Services Ltd

Reported period: –

View the government filing

Average time to pay

36 days

Register median: 31 days

Invoices paid late

22%

Register median: 14%

Standard payment terms

7 days

Declared in this filing

These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.

Already waiting for payment?

Check your own invoice.

Use your amount and dates to estimate late-payment interest and fixed compensation.

11 filings

How payments have changed

Late payments down 9 percentage pointsCompared with the previous filing

Ocu Utility Services Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H2 170%25%50%0d30d60dH2 17H1 18H2 18H1 19H2 19H1 20H2 20H1 21H2 21H2 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
View 6 recent filings
Recent payment filings by Ocu Utility Services Ltd
Period endingDays to payPaid lateWithin 30 daysOver 60 days
30 April 20263622%54%11%
31 October 20253331%55%7%
31 October 2021280%57%1%
30 April 2021270%54%1%
31 October 2020280%52%2%
30 April 2020290%49%3%

More from the filing

Payment terms and invoice breakdown
Standard payment terms
7 days
Maximum contractual period
60 days
Paid within 30 days
54%
Paid in 31–60 days
35%
Paid after 60 days
11%
Not paid because of a dispute
39%

The company’s own wording

We pay according to supplier terms; but we make weekly payment BACS payment runs to ensure late payments are kept to a minimum.
RetentionDeclared
Standard retention rate
5%
In all construction contracts
No
Same terms as their own client
No
Default position is retention is taken on all, however there are scopes of work that we do not take retention on – and this is assessed on a per contract basis.

Common questions

How long does Ocu Utility Services Ltd take to pay its suppliers?

Ocu Utility Services Ltd reported an average of 36 days to pay an invoice for 1 November 2025 to 30 April 2026, with 54% of invoices paid within 30 days and 11% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.

Does Ocu Utility Services Ltd pay late?

By its own filing, 22% of Ocu Utility Services Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is down 9 points on its previous filing (31% for the period to 31 October 2025).

Does Ocu Utility Services Ltd hold retention?

Yes. Ocu Utility Services Ltd declares retention clauses in its construction contracts at a standard rate of 5%, though not in all of them. The filing's own wording is quoted above.

Can I charge Ocu Utility Services Ltd interest on a late invoice?

Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.