Skip to content
fulcrum
Contact

Supplier payment record · SC220049

Ocs Technical Services Ltd

Reported period: –

View the government filing

Average time to pay

31 days

Register median: 31 days

Invoices paid late

31%

Register median: 14%

Standard payment terms

55 days

Declared in this filing

These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.

Already waiting for payment?

Check your own invoice.

Use your amount and dates to estimate late-payment interest and fixed compensation.

18 filings

How payments have changed

Late payments up 6 percentage pointsCompared with the previous filing

Ocs Technical Services Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H1 180%37.5%75%0d45d90dH1 18H1 19H1 20H1 21H1 22H1 23H1 24H1 25H2 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
View 6 recent filings
Recent payment filings by Ocs Technical Services Ltd
Period endingDays to payPaid lateWithin 30 daysOver 60 days
30 June 20263131%64%9%
31 December 20253025%62%10%
31 August 20255817%16%44%
28 February 20255810%19%46%
31 August 20245616%20%43%
29 February 20245913%17%47%

More from the filing

Payment terms and invoice breakdown
Standard payment terms
55 days
Maximum contractual period
55 days
Paid within 30 days
64%
Paid in 31–60 days
27%
Paid after 60 days
9%
Not paid because of a dispute
0%

The company’s own wording

55 days from date of invoice
RetentionDeclared
Standard retention rate
Not stated
In all construction contracts
Yes
Same terms as their own client
No

Common questions

How long does Ocs Technical Services Ltd take to pay its suppliers?

Ocs Technical Services Ltd reported an average of 31 days to pay an invoice for 1 January 2026 to 30 June 2026, with 64% of invoices paid within 30 days and 9% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.

Does Ocs Technical Services Ltd pay late?

By its own filing, 31% of Ocs Technical Services Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 6 points on its previous filing (25% for the period to 31 December 2025).

Does Ocs Technical Services Ltd hold retention?

Yes. Ocs Technical Services Ltd declares retention clauses in its construction contracts, in all of them. The filing's own wording is quoted above.

Can I charge Ocs Technical Services Ltd interest on a late invoice?

Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.