Average time to pay
36 days
Register median: 31 days
Supplier payment record · 00342778
Reported period: –
View the government filing36 days
Register median: 31 days
2%
Register median: 14%
30 to 60 days
Declared in this filing
These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.
Already waiting for payment?
Use your amount and dates to estimate late-payment interest and fixed compensation.
17 filings
Late payments down 2 percentage pointsCompared with the previous filing
| Period ending | Days to pay | Paid late | Within 30 days | Over 60 days |
|---|---|---|---|---|
| 27 August 2026 | 36 | 2% | 37% | 1% |
| 27 February 2026 | 35 | 4% | 40% | 1% |
| 31 August 2025 | 36 | 5% | 40% | 1% |
| 28 February 2025 | 37 | 6% | 36% | 1% |
| 1 September 2024 | 38 | 7% | 33% | 1% |
| 1 March 2024 | 36 | 9% | 40% | 2% |
Payment terms are agreed with suppliers and subcontractors as part of contract negotiations. The most frequently used payment term is 60 days from invoice date. Payment runs are typically done on a weekly basis.
Retention clauses are standard in engineering and construction contracts, but their inclusion depends on contract type and client requirements.
NG Bailey generally aligns retention clauses for subcontractors with those applied to us under the same contract, although the approach may differ depending on the specific contract or project. Our KPIs demonstrate that, in practice, we often hold less retention against our subcontractors than is held against us, reflecting our commitment to fair and balanced contract management.
NG Bailey Ltd reported an average of 36 days to pay an invoice for 28 February 2026 to 27 August 2026, with 37% of invoices paid within 30 days and 1% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
By its own filing, 2% of NG Bailey Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is down 2 points on its previous filing (4% for the period to 27 February 2026).
Yes. NG Bailey Ltd declares retention clauses in its construction contracts at a standard rate of 5%, though not in all of them. The filing's own wording is quoted above.
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.