Muse Places Ltd: how it pays its suppliers, from its own filing

Muse Places Ltd reports paying its suppliers in an average of 21 days, with 12% of invoices paid later than the agreed terms, for the period 1 January 2026 to 30 June 2026. Across the 1,496 companies that report on construction contracts, the median is 31 days and 14% late. Every figure below is the company’s own, approved by a director and published on the government register; this page reproduces it and says what it means for a subcontractor.

21 days

Average days to pay

longer than 16% of the 1,496 filers; median 31 days

12%

Paid later than agreed

a higher share than 43% of filers; median 14%

87%

Paid within 30 days

3% took longer than 60 days

The terms it declares

Standard payment terms
14 to 75 days
Maximum contractual period
75 days
Paid in 31 to 60 days
10%
Paid after 60 days
3%
Not paid because of a dispute
17%
Filed on
10 July 2026

Their standard terms, in their words

Our standard payment terms are between 14 and 75 days,

Every filing since Jun 2018

Muse Places Ltd has filed 17 times. The share paid late is up 1 points on the previous filing, and the average days to pay unchanged. The first filing, for the period to 30 June 2018, reported 42 days and 30% late.

Muse Places Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H1 180%25%50%0d30d60dH1 18H1 19H1 20H1 21H1 22H1 23H1 24H1 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
The last six filings by Muse Places Ltd
Period toDays to payPaid lateWithin 30 daysOver 60 days
30 June 20262112%87%3%
31 December 20252111%88%3%
30 June 20252112%86%3%
31 December 20242012%87%3%
30 June 20242114%86%3%
31 December 20232114%85%5%

Retention

Retention clauses in construction contracts
yes
Standard retention rate
5%
In all construction contracts
yes
Same terms they receive from their own client
yes
On parity with their client
Value of retention withheld from suppliers is equal to the value of retention withheld by clients.

What this means if you are pricing work for them

The share paid later than agreed is the number to read first, because a short term makes an invoice late sooner and a long one hides lateness inside the term. Muse Places Ltd is at or below the median on that measure. The average days to pay sits under the median.

On a 30-day term this company’s average lands inside the term, so a late invoice is the exception. When one is late, the calculator shows what statutory interest and the fixed sum add, which the law lets you charge without a clause.

Against the official benchmark: the Department for Business and Trade’s statistics for 2025, published 14 July 2026, put large construction businesses at 33 days to pay with 14% of invoices late by number (13% by value), and all large businesses at 32 days and 15% late. Muse Places Ltd is at or inside the sector figure on days. Its late share is at or below the sector figure.

What the register does not show: it is self-reported, large companies only, and the filing covers the whole company, not your contract. Read it alongside the notice rules that decide what you are actually owed, and keep your own dates.

Questions subcontractors ask about Muse Places Ltd

How long does Muse Places Ltd take to pay its suppliers?
Muse Places Ltd reported an average of 21 days to pay an invoice for 1 January 2026 to 30 June 2026, with 87% of invoices paid within 30 days and 3% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
Does Muse Places Ltd pay late?
By its own filing, 12% of Muse Places Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 1 points on its previous filing (11% for the period to 31 December 2025).
Does Muse Places Ltd hold retention?
Yes. Muse Places Ltd declares retention clauses in its construction contracts at a standard rate of 5%, in all of them. The filing's own wording is quoted above.
Can I charge Muse Places Ltd interest on a late invoice?
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.

Source: the company’s own report on the government’s payment practices service, report 112728, made under the Reporting on Payment Practices and Performance Regulations 2017 and reproduced under the Open Government Licence v3.0. Register copy taken 2 October 2026; comparisons are against the latest filing of each of the 1,496 companies declaring construction contracts. Figures are as filed, not judged. Not legal advice.