filing to 31 March 2026

// payment practices, as filed · company 08707642

Mtc Operations Ltd: how it pays its suppliers, from its own filing

Mtc Operations Ltd reports paying its suppliers in an average of 42 days, with 45% of invoices paid later than the agreed terms, for the period 1 October 2025 to 31 March 2026. Across the 1,496 companies that report on construction contracts, the median is 31 days and 14% late. Every figure below is the company’s own, approved by a director and published on the government register; this page reproduces it and says what it means for a subcontractor.

42 days

Average days to pay

longer than 75% of the 1,496 filers; median 31 days

45%

Paid later than agreed

a higher share than 91% of filers; median 14%

49%

Paid within 30 days

10% took longer than 60 days

The terms it declares

Standard payment terms
30 to 45 days
Maximum contractual period
60 days
Paid in 31 to 60 days
41%
Paid after 60 days
10%
Not paid because of a dispute
0%
Filed on
25 June 2026

Their standard terms, in their words

Standard payment terms are 45 days for suppliers with 50 or more employees, 30 days for those with less than 50 employees.

Their explanation

Our policy is that we endeavour to adhere to the Prompt Payment Code (PPC) in relation to payment terms, and aim to pay at least 95% of invoices within 45 days, including payment SME's within average of 30 days.

Every filing since Sep 2019

Mtc Operations Ltd has filed 14 times. The share paid late is up 17 points on the previous filing, and the average days to pay up 5 days. The first filing, for the period to 30 September 2019, reported 41 days and 66% late.

Mtc Operations Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H2 190%37.5%75%0d45d90dH2 19H1 20H2 20H1 21H2 21H1 22H2 22H1 23H2 23H1 24H2 24H1 25H2 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
The last six filings by Mtc Operations Ltd
Period toDays to payPaid lateWithin 30 daysOver 60 days
31 March 20264245%49%10%
30 September 20253728%52%10%
31 March 20253532%48%9%
30 September 20243626%50%13%
31 March 20244337%40%19%
30 September 20234432%43%22%

Retention

Retention clauses in construction contracts
yes
Standard retention rate
not stated
In all construction contracts
no
Same terms they receive from their own client
no
When they apply retention
Determined on an individual basis depending on the scope and scale of the specific contract works.

What this means if you are pricing work for them

The share paid later than agreed is the number to read first, because a short term makes an invoice late sooner and a long one hides lateness inside the term. Mtc Operations Ltd is above the median on that measure, so build the delay into your cash flow before you sign. The average days to pay sits over the median.

A worked example on a 30-day term: an invoice of £10,000.00 paid on this company’s average, 12 days after the final date, carries £38.63 of statutory interest at 11.75% plus the fixed sum, £138.63 in all, which the law lets you add without a clause. Run your own figures.

Against the official benchmark: the Department for Business and Trade’s statistics for 2025, published 14 July 2026, put large construction businesses at 33 days to pay with 14% of invoices late by number (13% by value), and all large businesses at 32 days and 15% late. Mtc Operations Ltd is slower than the sector figure. Its late share is above the sector figure.

What the register does not show: it is self-reported, large companies only, and the filing covers the whole company, not your contract. Read it alongside the notice rules that decide what you are actually owed, and keep your own dates.

Questions subcontractors ask about Mtc Operations Ltd

How long does Mtc Operations Ltd take to pay its suppliers?
Mtc Operations Ltd reported an average of 42 days to pay an invoice for 1 October 2025 to 31 March 2026, with 49% of invoices paid within 30 days and 10% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
Does Mtc Operations Ltd pay late?
By its own filing, 45% of Mtc Operations Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 17 points on its previous filing (28% for the period to 30 September 2025).
Does Mtc Operations Ltd hold retention?
Yes. Mtc Operations Ltd declares retention clauses in its construction contracts, though not in all of them. The filing's own wording is quoted above.
Can I charge Mtc Operations Ltd interest on a late invoice?
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.

Source: the company’s own report on the government’s payment practices service, report 112422, made under the Reporting on Payment Practices and Performance Regulations 2017 and reproduced under the Open Government Licence v3.0. Register copy taken 2 October 2026; comparisons are against the latest filing of each of the 1,496 companies declaring construction contracts. Figures are as filed, not judged. Not legal advice.