Average time to pay
38 days
Register median: 31 days
Supplier payment record · 00324340
Reported period: –
View the government filing38 days
Register median: 31 days
31%
Register median: 14%
7 to 90 days
Declared in this filing
These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.
Already waiting for payment?
Use your amount and dates to estimate late-payment interest and fixed compensation.
16 filings
Late payments up 6 percentage pointsCompared with the previous filing
| Period ending | Days to pay | Paid late | Within 30 days | Over 60 days |
|---|---|---|---|---|
| 30 June 2026 | 38 | 31% | 67% | 15% |
| 31 December 2025 | 37 | 25% | 70% | 12% |
| 30 June 2025 | 38 | 35% | 64% | 17% |
| 31 December 2024 | 37 | 26% | 67% | 13% |
| 30 June 2024 | 39 | 32% | 67% | 14% |
| 31 December 2023 | 37 | 19% | 70% | 12% |
Payment terms are negotiated for each contract
If the value exceeds £100,000 for construction and building works
n/a
Linde Material Handling (UK) Ltd reported an average of 38 days to pay an invoice for 1 January 2026 to 30 June 2026, with 67% of invoices paid within 30 days and 15% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
By its own filing, 31% of Linde Material Handling (UK) Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 6 points on its previous filing (25% for the period to 31 December 2025).
Yes. Linde Material Handling (UK) Ltd declares retention clauses in its construction contracts at a standard rate of 2%, though not in all of them. The filing's own wording is quoted above.
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.