Skip to content
fulcrum
Contact
filing to 30 June 2026

// payment practices, as filed · company 01372978

Kone Public Ltd Company: how it pays its suppliers, from its own filing

Kone Public Ltd Company reports paying its suppliers in an average of 51 days, with 27% of invoices paid later than the agreed terms, for the period 1 January 2026 to 30 June 2026. Across the 1,496 companies that report on construction contracts, the median is 31 days and 14% late. Every figure below is the company’s own, approved by a director and published on the government register; this page reproduces it and says what it means for a subcontractor.

51 days

Average days to pay

longer than 87% of the 1,496 filers; median 31 days

27%

Paid later than agreed

a higher share than 75% of filers; median 14%

40%

Paid within 30 days

14% took longer than 60 days

The terms it declares

Standard payment terms
0 to 60 days
Maximum contractual period
60 days
Paid in 31 to 60 days
46%
Paid after 60 days
14%
Not paid because of a dispute
78%
Filed on
31 July 2026

Their standard terms, in their words

14-60 days

Every filing since Jun 2018

Kone Public Ltd Company has filed 17 times. The share paid late is up 4 points on the previous filing, and the average days to pay up 7 days. The first filing, for the period to 30 June 2018, reported 52 days and 57% late.

Kone Public Ltd Company: share of invoices paid late (bars) and average days to pay (line), every filing since H1 180%37.5%75%0d30d60dH1 18H1 19H1 20H1 21H1 22H1 23H1 24H1 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
The last six filings by Kone Public Ltd Company
Period toDays to payPaid lateWithin 30 daysOver 60 days
30 June 20265127%40%14%
31 December 20254423%50%8%
30 June 20254421%49%9%
31 December 20244820%51%8%
30 June 20244615%49%7%
31 December 20234716%44%7%

Retention

Retention clauses in construction contracts
yes
Standard retention rate
15%
In all construction contracts
no
Same terms they receive from their own client
yes
When they apply retention
Only subcontractors supplying installation labor for new equipment installations and modernizations.
On parity with their client
The installation elements of our contracts is only a portion of the contract. The quality retention represents 15% or £500 which ever is greater of the agreed installation price which is significantly less than the total contracted price.

What this means if you are pricing work for them

The share paid later than agreed is the number to read first, because a short term makes an invoice late sooner and a long one hides lateness inside the term. Kone Public Ltd Company is above the median on that measure, so build the delay into your cash flow before you sign. The average days to pay sits over the median.

A worked example on a 30-day term: an invoice of £10,000.00 paid on this company’s average, 21 days after the final date, carries £67.60 of statutory interest at 11.75% plus the fixed sum, £167.60 in all, which the law lets you add without a clause. Run your own figures.

Against the official benchmark: the Department for Business and Trade’s statistics for 2025, published 14 July 2026, put large construction businesses at 33 days to pay with 14% of invoices late by number (13% by value), and all large businesses at 32 days and 15% late. Kone Public Ltd Company is slower than the sector figure. Its late share is above the sector figure.

What the register does not show: it is self-reported, large companies only, and the filing covers the whole company, not your contract. Read it alongside the notice rules that decide what you are actually owed, and keep your own dates.

Questions subcontractors ask about Kone Public Ltd Company

How long does Kone Public Ltd Company take to pay its suppliers?
Kone Public Ltd Company reported an average of 51 days to pay an invoice for 1 January 2026 to 30 June 2026, with 40% of invoices paid within 30 days and 14% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
Does Kone Public Ltd Company pay late?
By its own filing, 27% of Kone Public Ltd Company's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 4 points on its previous filing (23% for the period to 31 December 2025).
Does Kone Public Ltd Company hold retention?
Yes. Kone Public Ltd Company declares retention clauses in its construction contracts at a standard rate of 15%, though not in all of them. The filing's own wording is quoted above.
Can I charge Kone Public Ltd Company interest on a late invoice?
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.

Source: the company’s own report on the government’s payment practices service, report 115819, made under the Reporting on Payment Practices and Performance Regulations 2017 and reproduced under the Open Government Licence v3.0. Register copy taken 2 October 2026; comparisons are against the latest filing of each of the 1,496 companies declaring construction contracts. Figures are as filed, not judged. Not legal advice.