Houlihan Lokey UK Ltd: how it pays its suppliers, from its own filing

Houlihan Lokey UK Ltd reports paying its suppliers in an average of 24 days, with 17% of invoices paid later than the agreed terms, for the period 1 April 2025 to 30 September 2025. Across the 1,496 companies that report on construction contracts, the median is 31 days and 14% late. Every figure below is the company’s own, approved by a director and published on the government register; this page reproduces it and says what it means for a subcontractor.

24 days

Average days to pay

longer than 25% of the 1,496 filers; median 31 days

17%

Paid later than agreed

a higher share than 56% of filers; median 14%

83%

Paid within 30 days

7% took longer than 60 days

The terms it declares

Standard payment terms
0 to 30 days
Maximum contractual period
30 days
Paid in 31 to 60 days
10%
Paid after 60 days
7%
Not paid because of a dispute
0%
Filed on
31 October 2025

Their standard terms, in their words

HL UK Limited does not have standard payment terms with its qualifying suppliers. Terms are agreed with each supplier in qualifying contracts, typically based on supplier standard terms.

Every filing since Sep 2024

Houlihan Lokey UK Ltd has filed 4 times. The share paid late is down 11 points on the previous filing, and the average days to pay down 2 days. The first filing, for the period to 30 September 2024, reported 24 days and 23% late.

Houlihan Lokey UK Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H2 240%25%50%0d30d60dH2 24H1 25H2 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
The last six filings by Houlihan Lokey UK Ltd
Period toDays to payPaid lateWithin 30 daysOver 60 days
31 March 20262219%81%6%
30 September 20252417%83%7%
31 March 20252628%72%8%
30 September 20242423%77%7%

Retention

This filing declares no retention clauses in its construction contracts. If your subcontract with Houlihan Lokey UK Ltd does hold retention, the contract governs; the retention piece explains how to get it released.

What this means if you are pricing work for them

The share paid later than agreed is the number to read first, because a short term makes an invoice late sooner and a long one hides lateness inside the term. Houlihan Lokey UK Ltd is above the median on that measure, so build the delay into your cash flow before you sign. The average days to pay sits under the median.

On a 30-day term this company’s average lands inside the term, so a late invoice is the exception. When one is late, the calculator shows what statutory interest and the fixed sum add, which the law lets you charge without a clause.

Against the official benchmark: the Department for Business and Trade’s statistics for 2025, published 14 July 2026, put large construction businesses at 33 days to pay with 14% of invoices late by number (13% by value), and all large businesses at 32 days and 15% late. Houlihan Lokey UK Ltd is at or inside the sector figure on days. Its late share is above the sector figure.

What the register does not show: it is self-reported, large companies only, and the filing covers the whole company, not your contract. Read it alongside the notice rules that decide what you are actually owed, and keep your own dates.

Questions subcontractors ask about Houlihan Lokey UK Ltd

How long does Houlihan Lokey UK Ltd take to pay its suppliers?
Houlihan Lokey UK Ltd reported an average of 24 days to pay an invoice for 1 April 2025 to 30 September 2025, with 83% of invoices paid within 30 days and 7% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
Does Houlihan Lokey UK Ltd pay late?
By its own filing, 17% of Houlihan Lokey UK Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is down 11 points on its previous filing (28% for the period to 31 March 2025).
Does Houlihan Lokey UK Ltd hold retention?
Houlihan Lokey UK Ltd declares no retention clauses in its construction contracts in this filing. Your subcontract governs; if it holds retention, the contract terms decide when it is released.
Can I charge Houlihan Lokey UK Ltd interest on a late invoice?
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.

Source: the company’s own report on the government’s payment practices service, report 104780, made under the Reporting on Payment Practices and Performance Regulations 2017 and reproduced under the Open Government Licence v3.0. Register copy taken 2 October 2026; comparisons are against the latest filing of each of the 1,496 companies declaring construction contracts. Figures are as filed, not judged. Not legal advice.