filing to 1 August 2026

// payment practices, as filed · company 00676533

Harrods International Ltd: how it pays its suppliers, from its own filing

Harrods International Ltd reports paying its suppliers in an average of 48 days, with 46% of invoices paid later than the agreed terms, for the period 1 February 2026 to 1 August 2026. Across the 1,496 companies that report on construction contracts, the median is 31 days and 14% late. Every figure below is the company’s own, approved by a director and published on the government register; this page reproduces it and says what it means for a subcontractor.

48 days

Average days to pay

longer than 83% of the 1,496 filers; median 31 days

46%

Paid later than agreed

a higher share than 91% of filers; median 14%

6%

Paid within 30 days

18% took longer than 60 days

The terms it declares

Standard payment terms
30 to 60 days
Maximum contractual period
75 days
Paid in 31 to 60 days
76%
Paid after 60 days
18%
Not paid because of a dispute
0%
Filed on
28 August 2026

Their standard terms, in their words

• Merchandise 30 days. • Non-Merchandise 60 days Any invoices due will be paid the following Monday in line with Harrods’ weekly payment run.

Every filing since Aug 2018

Harrods International Ltd has filed 17 times. The share paid late is up 4 points on the previous filing, and the average days to pay up 12 days. The first filing, for the period to 4 August 2018, reported 35 days and 19% late.

Harrods International Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H2 180%50%100%0d30d60dH2 18H2 19H2 20H2 21H2 22H2 23H2 24H2 25H2 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
The last six filings by Harrods International Ltd
Period toDays to payPaid lateWithin 30 daysOver 60 days
1 August 20264846%6%18%
31 January 20263642%17%3%
2 August 20253741%14%11%
1 February 20253748%19%7%
3 August 20244055%16%14%
3 February 20243356%39%8%

Retention

Retention clauses in construction contracts
yes
Standard retention rate
5%
In all construction contracts
no
Same terms they receive from their own client
no
When they apply retention
All of our major construction projects are managed under a JCT Form of Contract, typically either a Standard Building Contract or a Design and Build Contract. In both form of contract a retention of 5% is held on all payments made to the Contractor throughout the construction phase of the project. This does not apply to service suppliers on construction projects, such as architects, designers and surveyors.

What this means if you are pricing work for them

The share paid later than agreed is the number to read first, because a short term makes an invoice late sooner and a long one hides lateness inside the term. Harrods International Ltd is above the median on that measure, so build the delay into your cash flow before you sign. The average days to pay sits over the median.

A worked example on a 30-day term: an invoice of £10,000.00 paid on this company’s average, 18 days after the final date, carries £57.95 of statutory interest at 11.75% plus the fixed sum, £157.95 in all, which the law lets you add without a clause. Run your own figures.

Against the official benchmark: the Department for Business and Trade’s statistics for 2025, published 14 July 2026, put large construction businesses at 33 days to pay with 14% of invoices late by number (13% by value), and all large businesses at 32 days and 15% late. Harrods International Ltd is slower than the sector figure. Its late share is above the sector figure.

What the register does not show: it is self-reported, large companies only, and the filing covers the whole company, not your contract. Read it alongside the notice rules that decide what you are actually owed, and keep your own dates.

Questions subcontractors ask about Harrods International Ltd

How long does Harrods International Ltd take to pay its suppliers?
Harrods International Ltd reported an average of 48 days to pay an invoice for 1 February 2026 to 1 August 2026, with 6% of invoices paid within 30 days and 18% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
Does Harrods International Ltd pay late?
By its own filing, 46% of Harrods International Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 4 points on its previous filing (42% for the period to 31 January 2026).
Does Harrods International Ltd hold retention?
Yes. Harrods International Ltd declares retention clauses in its construction contracts at a standard rate of 5%, though not in all of them. The filing's own wording is quoted above.
Can I charge Harrods International Ltd interest on a late invoice?
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.

Source: the company’s own report on the government’s payment practices service, report 116686, made under the Reporting on Payment Practices and Performance Regulations 2017 and reproduced under the Open Government Licence v3.0. Register copy taken 2 October 2026; comparisons are against the latest filing of each of the 1,496 companies declaring construction contracts. Figures are as filed, not judged. Not legal advice.