Hallam Land Management Ltd: how it pays its suppliers, from its own filing

Hallam Land Management Ltd reports paying its suppliers in an average of 36 days, with 55% of invoices paid later than the agreed terms, for the period 1 January 2026 to 30 June 2026. Across the 1,496 companies that report on construction contracts, the median is 31 days and 14% late. Every figure below is the company’s own, approved by a director and published on the government register; this page reproduces it and says what it means for a subcontractor.

36 days

Average days to pay

longer than 62% of the 1,496 filers; median 31 days

55%

Paid later than agreed

a higher share than 94% of filers; median 14%

45%

Paid within 30 days

9% took longer than 60 days

The terms it declares

Standard payment terms
30 days
Maximum contractual period
30 days
Paid in 31 to 60 days
46%
Paid after 60 days
9%
Not paid because of a dispute
0%
Filed on
30 July 2026

Their standard terms, in their words

Hallam Land's standard supplier payment terms are 30 days from date of invoice. This is subject to anything contained within a specific contract. Due date is calculated by applying agreed terms to the invoice date. If an invoice falls due during a weekend or bank holiday, the payment transaction is executed on the following business day. All invoices received are required to comply with our invoice requirements, otherwise we reserve the right to not process the document for payment until it has been corrected. Terms are negotiated and agreed with suppliers on initial engagement.

Every filing since Jun 2018

Hallam Land Management Ltd has filed 17 times. The share paid late is up 7 points on the previous filing, and the average days to pay up 8 days. The first filing, for the period to 30 June 2018, reported 26 days and 48% late.

Hallam Land Management Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H1 180%37.5%75%0d30d60dH1 18H1 19H1 20H1 21H1 22H1 23H1 24H1 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
The last six filings by Hallam Land Management Ltd
Period toDays to payPaid lateWithin 30 daysOver 60 days
30 June 20263655%45%9%
31 December 20252848%72%3%
30 June 20252436%83%1%
31 December 20242845%74%3%
30 June 20242756%67%4%
31 December 20232548%78%4%

Retention

Retention clauses in construction contracts
yes
Standard retention rate
not stated
In all construction contracts
yes
Same terms they receive from their own client
no

What this means if you are pricing work for them

The share paid later than agreed is the number to read first, because a short term makes an invoice late sooner and a long one hides lateness inside the term. Hallam Land Management Ltd is above the median on that measure, so build the delay into your cash flow before you sign. The average days to pay sits over the median.

A worked example on a 30-day term: an invoice of £10,000.00 paid on this company’s average, 6 days after the final date, carries £19.32 of statutory interest at 11.75% plus the fixed sum, £119.32 in all, which the law lets you add without a clause. Run your own figures.

Against the official benchmark: the Department for Business and Trade’s statistics for 2025, published 14 July 2026, put large construction businesses at 33 days to pay with 14% of invoices late by number (13% by value), and all large businesses at 32 days and 15% late. Hallam Land Management Ltd is slower than the sector figure. Its late share is above the sector figure.

What the register does not show: it is self-reported, large companies only, and the filing covers the whole company, not your contract. Read it alongside the notice rules that decide what you are actually owed, and keep your own dates.

Questions subcontractors ask about Hallam Land Management Ltd

How long does Hallam Land Management Ltd take to pay its suppliers?
Hallam Land Management Ltd reported an average of 36 days to pay an invoice for 1 January 2026 to 30 June 2026, with 45% of invoices paid within 30 days and 9% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
Does Hallam Land Management Ltd pay late?
By its own filing, 55% of Hallam Land Management Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 7 points on its previous filing (48% for the period to 31 December 2025).
Does Hallam Land Management Ltd hold retention?
Yes. Hallam Land Management Ltd declares retention clauses in its construction contracts, in all of them. The filing's own wording is quoted above.
Can I charge Hallam Land Management Ltd interest on a late invoice?
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.

Source: the company’s own report on the government’s payment practices service, report 115276, made under the Reporting on Payment Practices and Performance Regulations 2017 and reproduced under the Open Government Licence v3.0. Register copy taken 2 October 2026; comparisons are against the latest filing of each of the 1,496 companies declaring construction contracts. Figures are as filed, not judged. Not legal advice.