Greene King Brewing and Retailing Ltd: how it pays its suppliers, from its own filing

Greene King Brewing and Retailing Ltd reports paying its suppliers in an average of 45 days, with 6% of invoices paid later than the agreed terms, for the period 1 January 2026 to 30 June 2026. Across the 1,496 companies that report on construction contracts, the median is 31 days and 14% late. Every figure below is the company’s own, approved by a director and published on the government register; this page reproduces it and says what it means for a subcontractor.

45 days

Average days to pay

longer than 80% of the 1,496 filers; median 31 days

6%

Paid later than agreed

a higher share than 22% of filers; median 14%

19%

Paid within 30 days

14% took longer than 60 days

The terms it declares

Standard payment terms
60 days
Maximum contractual period
90 days
Paid in 31 to 60 days
67%
Paid after 60 days
14%
Not paid because of a dispute
0%
Filed on
30 July 2026

Their standard terms, in their words

Our standard payment terms are 60 days following the end of the month of the invoice date

Every filing since Oct 2017

Greene King Brewing and Retailing Ltd has filed 19 times. The share paid late is up 1 points on the previous filing, and the average days to pay down 1 days. The first filing, for the period to 31 October 2017, reported 40 days and 10% late.

Greene King Brewing and Retailing Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H2 170%12.5%25%0d30d60dH2 17H2 18H2 19H2 20H1 21H1 22H1 23H1 24H1 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
The last six filings by Greene King Brewing and Retailing Ltd
Period toDays to payPaid lateWithin 30 daysOver 60 days
30 June 2026456%19%14%
31 December 2025465%21%13%
30 June 2025454%20%11%
31 December 2024454%20%13%
30 June 20244315%24%11%
31 December 2023445%27%16%

Retention

Retention clauses in construction contracts
yes
Standard retention rate
5%
In all construction contracts
no
Same terms they receive from their own client
no
When they apply retention
Retention clauses are not automatically applied to every supplier contract. Retention is generally only included under the Contractor Framework / Works Order route for contractor-led construction or refurbishment works where the relevant Works Order specifies the retention percentage.

What this means if you are pricing work for them

The share paid later than agreed is the number to read first, because a short term makes an invoice late sooner and a long one hides lateness inside the term. Greene King Brewing and Retailing Ltd is at or below the median on that measure. The average days to pay sits over the median.

A worked example on a 30-day term: an invoice of £10,000.00 paid on this company’s average, 15 days after the final date, carries £48.29 of statutory interest at 11.75% plus the fixed sum, £148.29 in all, which the law lets you add without a clause. Run your own figures.

Against the official benchmark: the Department for Business and Trade’s statistics for 2025, published 14 July 2026, put large construction businesses at 33 days to pay with 14% of invoices late by number (13% by value), and all large businesses at 32 days and 15% late. Greene King Brewing and Retailing Ltd is slower than the sector figure. Its late share is at or below the sector figure.

What the register does not show: it is self-reported, large companies only, and the filing covers the whole company, not your contract. Read it alongside the notice rules that decide what you are actually owed, and keep your own dates.

Questions subcontractors ask about Greene King Brewing and Retailing Ltd

How long does Greene King Brewing and Retailing Ltd take to pay its suppliers?
Greene King Brewing and Retailing Ltd reported an average of 45 days to pay an invoice for 1 January 2026 to 30 June 2026, with 19% of invoices paid within 30 days and 14% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
Does Greene King Brewing and Retailing Ltd pay late?
By its own filing, 6% of Greene King Brewing and Retailing Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 1 points on its previous filing (5% for the period to 31 December 2025).
Does Greene King Brewing and Retailing Ltd hold retention?
Yes. Greene King Brewing and Retailing Ltd declares retention clauses in its construction contracts at a standard rate of 5%, though not in all of them. The filing's own wording is quoted above.
Can I charge Greene King Brewing and Retailing Ltd interest on a late invoice?
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.

Source: the company’s own report on the government’s payment practices service, report 115018, made under the Reporting on Payment Practices and Performance Regulations 2017 and reproduced under the Open Government Licence v3.0. Register copy taken 2 October 2026; comparisons are against the latest filing of each of the 1,496 companies declaring construction contracts. Figures are as filed, not judged. Not legal advice.