Supplier payment record · NI013563

Fp Mccann Ltd

Reported period: –

View the government filing

Average time to pay

27 days

Register median: 31 days

Invoices paid late

2%

Register median: 14%

Standard payment terms

30 days

Declared in this filing

These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.

Already waiting for payment?

Check your own invoice.

Use your amount and dates to estimate late-payment interest and fixed compensation.

17 filings

How payments have changed

Late payments unchangedCompared with the previous filing

Fp Mccann Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H1 180%12.5%25%0d30d60dH1 18H1 19H1 20H1 21H1 22H1 23H1 24H1 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
View 6 recent filings
Recent payment filings by Fp Mccann Ltd
Period endingDays to payPaid lateWithin 30 daysOver 60 days
30 June 2026272%58%4%
31 December 2025292%59%3%
30 June 2025273%62%3%
31 December 20242710%67%3%
30 June 20242810%66%3%
31 December 20232910%64%3%

More from the filing

Payment terms and invoice breakdown
Standard payment terms
30 days
Maximum contractual period
120 days
Paid within 30 days
58%
Paid in 31–60 days
38%
Paid after 60 days
4%
Not paid because of a dispute
1%

The company’s own wording

In general terms, the payment terms adopted by FP McCann are for invoices to be settled on the next payment run following the credit terms requested by the respective supplier. These terms cover a range of periods mostly payment falling due at the end of one or two months following the invoice date. Consequently, when the invoice is approved by the appropriate delegated authority, it is allocated for payment accordingly. There have been no changes to this policy during the reporting period. Payments made direct to bank accounts via BACS or via cheque. To ensure prompt payment and reduce the r…
RetentionNone declared

No retention clauses were declared in this filing.

Common questions

How long does Fp Mccann Ltd take to pay its suppliers?

Fp Mccann Ltd reported an average of 27 days to pay an invoice for 1 January 2026 to 30 June 2026, with 58% of invoices paid within 30 days and 4% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.

Does Fp Mccann Ltd pay late?

By its own filing, 2% of Fp Mccann Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is unchanged on its previous filing (2% for the period to 31 December 2025).

Does Fp Mccann Ltd hold retention?

Fp Mccann Ltd declares no retention clauses in its construction contracts in this filing. Your subcontract governs; if it holds retention, the contract terms decide when it is released.

Can I charge Fp Mccann Ltd interest on a late invoice?

Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.