F M Conway Ltd: how it pays its suppliers, from its own filing

F M Conway Ltd reports paying its suppliers in an average of 26 days, with 10% of invoices paid later than the agreed terms, for the period 1 January 2026 to 30 June 2026. Across the 1,496 companies that report on construction contracts, the median is 31 days and 14% late. Every figure below is the company’s own, approved by a director and published on the government register; this page reproduces it and says what it means for a subcontractor.

26 days

Average days to pay

longer than 31% of the 1,496 filers; median 31 days

10%

Paid later than agreed

a higher share than 36% of filers; median 14%

74%

Paid within 30 days

2% took longer than 60 days

The terms it declares

Standard payment terms
7 to 60 days
Maximum contractual period
60 days
Paid in 31 to 60 days
24%
Paid after 60 days
2%
Not paid because of a dispute
72%
Filed on
17 July 2026

Their standard terms, in their words

Standard payment terms are 30 days from receipt of a valid invoice. Non-Standard terms are agreed with Suppliers and Subcontractors to comply with specific statutory and/or client contractual requirements. Terms agreed range from 7 days to 60 days from month end of invoice received.

Every filing since Sep 2018

F M Conway Ltd has filed 16 times. The share paid late is up 1 points on the previous filing, and the average days to pay unchanged. The first filing, for the period to 30 September 2018, reported 31 days and 30% late.

F M Conway Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H2 180%25%50%0d30d60dH2 18H2 19H2 20H2 21H2 22H2 23H2 24H2 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
The last six filings by F M Conway Ltd
Period toDays to payPaid lateWithin 30 daysOver 60 days
30 June 20262610%74%2%
31 December 2025269%70%3%
31 March 20252611%69%3%
30 September 2024269%68%2%
31 March 20242711%65%3%
30 September 20232811%62%3%

Retention

Retention clauses in construction contracts
yes
Standard retention rate
5%
In all construction contracts
no
Same terms they receive from their own client
yes
When they apply retention
Retentions on construction contracts are only required in a minority of occasions where retention clauses are applied by the client.
On parity with their client
Retention clause applied to clients mirrors retention clause on our suppliers

What this means if you are pricing work for them

The share paid later than agreed is the number to read first, because a short term makes an invoice late sooner and a long one hides lateness inside the term. F M Conway Ltd is at or below the median on that measure. The average days to pay sits under the median.

On a 30-day term this company’s average lands inside the term, so a late invoice is the exception. When one is late, the calculator shows what statutory interest and the fixed sum add, which the law lets you charge without a clause.

Against the official benchmark: the Department for Business and Trade’s statistics for 2025, published 14 July 2026, put large construction businesses at 33 days to pay with 14% of invoices late by number (13% by value), and all large businesses at 32 days and 15% late. F M Conway Ltd is at or inside the sector figure on days. Its late share is at or below the sector figure.

What the register does not show: it is self-reported, large companies only, and the filing covers the whole company, not your contract. Read it alongside the notice rules that decide what you are actually owed, and keep your own dates.

Questions subcontractors ask about F M Conway Ltd

How long does F M Conway Ltd take to pay its suppliers?
F M Conway Ltd reported an average of 26 days to pay an invoice for 1 January 2026 to 30 June 2026, with 74% of invoices paid within 30 days and 2% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
Does F M Conway Ltd pay late?
By its own filing, 10% of F M Conway Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 1 points on its previous filing (9% for the period to 31 December 2025).
Does F M Conway Ltd hold retention?
Yes. F M Conway Ltd declares retention clauses in its construction contracts at a standard rate of 5%, though not in all of them. The filing's own wording is quoted above.
Can I charge F M Conway Ltd interest on a late invoice?
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.

Source: the company’s own report on the government’s payment practices service, report 112968, made under the Reporting on Payment Practices and Performance Regulations 2017 and reproduced under the Open Government Licence v3.0. Register copy taken 2 October 2026; comparisons are against the latest filing of each of the 1,496 companies declaring construction contracts. Figures are as filed, not judged. Not legal advice.