Supplier payment record · 10253456

E.On UK Steven’s Croft Ltd

Reported period: –

View the government filing

Average time to pay

18 days

Register median: 31 days

Invoices paid late

17%

Register median: 14%

Standard payment terms

0 to 81 days

Declared in this filing

These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.

Already waiting for payment?

Check your own invoice.

Use your amount and dates to estimate late-payment interest and fixed compensation.

6 filings

How payments have changed

Late payments down 21 percentage pointsCompared with the previous filing

E.On UK Steven’s Croft Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H2 230%25%50%0d45d90dH2 23H1 24H2 24H1 25H2 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
View 6 recent filings
Recent payment filings by E.On UK Steven’s Croft Ltd
Period endingDays to payPaid lateWithin 30 daysOver 60 days
30 June 20261817%84%3%
31 December 20252138%77%5%
30 June 20251447%89%0%
31 December 20241547%84%0%
30 June 20247433%54%26%
31 December 20232443%72%4%

More from the filing

Payment terms and invoice breakdown
Standard payment terms
0 to 81 days
Maximum contractual period
81 days
Paid within 30 days
84%
Paid in 31–60 days
13%
Paid after 60 days
3%
Not paid because of a dispute
0%

The company’s own wording

There are four standard payment terms: within 30 days due net; 45 days end of month net, due on 5th of following month, 30 days net; 15 days net. Variations can be agreed for individual circumstances
RetentionNone declared

No retention clauses were declared in this filing.

Common questions

How long does E.On UK Steven’s Croft Ltd take to pay its suppliers?

E.On UK Steven’s Croft Ltd reported an average of 18 days to pay an invoice for 1 January 2026 to 30 June 2026, with 84% of invoices paid within 30 days and 3% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.

Does E.On UK Steven’s Croft Ltd pay late?

By its own filing, 17% of E.On UK Steven’s Croft Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is down 21 points on its previous filing (38% for the period to 31 December 2025).

Does E.On UK Steven’s Croft Ltd hold retention?

E.On UK Steven’s Croft Ltd declares no retention clauses in its construction contracts in this filing. Your subcontract governs; if it holds retention, the contract terms decide when it is released.

Can I charge E.On UK Steven’s Croft Ltd interest on a late invoice?