Average time to pay
52 days
Register median: 31 days
Supplier payment record · 00614864
Reported period: –
View the government filing52 days
Register median: 31 days
64%
Register median: 14%
7 to 91 days
Declared in this filing
These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.
Already waiting for payment?
Use your amount and dates to estimate late-payment interest and fixed compensation.
17 filings
Late payments up 7 percentage pointsCompared with the previous filing
| Period ending | Days to pay | Paid late | Within 30 days | Over 60 days |
|---|---|---|---|---|
| 30 June 2026 | 52 | 64% | 21% | 24% |
| 31 December 2025 | 46 | 57% | 26% | 16% |
| 30 June 2025 | 46 | 53% | 28% | 15% |
| 31 December 2024 | 47 | 55% | 28% | 17% |
| 30 June 2024 | 62 | 58% | 21% | 29% |
| 31 December 2023 | 51 | 36% | 30% | 17% |
Where payment relates to services provided by a subcontractor, payment of any sum ascertained as due in accordance with Vistry’s Trade Contract Terms & Conditions shall become due 14 days after the application date (the “payment due date”). The final date for payment is 14 days after the payment due date (i.e. 30 days from the application date). Where the payment relates to goods or services the terms differ and are required to be paid the month after the month of the date of the invoice, unless agreed otherwise.
Most standard contracts include a 5% retention. There are some exceptions to this whereby a zero or capped retention policy may be in place, agreed by exception.
The retention amounts deducted from subcontractor payments will be applied at the same percentage or a lower percentage than that deducted from the company.
Countryside Properties (UK) Ltd reported an average of 52 days to pay an invoice for 1 January 2026 to 30 June 2026, with 21% of invoices paid within 30 days and 24% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
By its own filing, 64% of Countryside Properties (UK) Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 7 points on its previous filing (57% for the period to 31 December 2025).
Yes. Countryside Properties (UK) Ltd declares retention clauses in its construction contracts at a standard rate of 5%, though not in all of them. The filing's own wording is quoted above.
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.