Supplier payment record · 00610201

Costain Ltd

Reported period: –

View the government filing

Average time to pay

25 days

Register median: 31 days

Invoices paid late

18%

Register median: 14%

Standard payment terms

7 days

Declared in this filing

These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.

Already waiting for payment?

Check your own invoice.

Use your amount and dates to estimate late-payment interest and fixed compensation.

17 filings

How payments have changed

Late payments up 3 percentage pointsCompared with the previous filing

Costain Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H1 180%37.5%75%0d30d60dH1 18H1 19H1 20H1 21H1 22H1 23H1 24H1 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
View 6 recent filings
Recent payment filings by Costain Ltd
Period endingDays to payPaid lateWithin 30 daysOver 60 days
30 June 20262518%78%3%
31 December 20252015%84%4%
30 June 20252212%82%3%
31 December 20243114%88%2%
30 June 20242013%85%3%
31 December 20231910%88%2%

More from the filing

Payment terms and invoice breakdown
Standard payment terms
7 days
Maximum contractual period
60 days
Paid within 30 days
78%
Paid in 31–60 days
19%
Paid after 60 days
3%
Not paid because of a dispute
0%

The company’s own wording

Payment terms are agreed with suppliers and subcontractors as part of the contract arrangement and invoices must show the order number. Terms very between 7 days where we have some rental invoices and payment is made once the invoice is processed to 60 days from the date of invoices. The most frequent payment term for supplier within the reporting period is 30 days from the date of the invoice with payment to these suppliers generally made after receiving the statement from the supplier.
RetentionDeclared
Standard retention rate
Not stated
In all construction contracts
No
Same terms as their own client
No
Agreements are made with subcontractors on projects regarding if a contract includes a retention clause or not, this is down to the discretion of the site commercial team

Common questions

How long does Costain Ltd take to pay its suppliers?

Costain Ltd reported an average of 25 days to pay an invoice for 1 January 2026 to 30 June 2026, with 78% of invoices paid within 30 days and 3% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.

Does Costain Ltd pay late?

By its own filing, 18% of Costain Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 3 points on its previous filing (15% for the period to 31 December 2025).

Does Costain Ltd hold retention?

Yes. Costain Ltd declares retention clauses in its construction contracts, though not in all of them. The filing's own wording is quoted above.

Can I charge Costain Ltd interest on a late invoice?

Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.