Skip to content
fulcrum
Contact

Supplier payment record · 07306352

Colt Data Centre Services UK Ltd

Reported period: –

View the government filing

Average time to pay

34 days

Register median: 31 days

Invoices paid late

26%

Register median: 14%

Standard payment terms

0 to 90 days

Declared in this filing

These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.

Already waiting for payment?

Check your own invoice.

Use your amount and dates to estimate late-payment interest and fixed compensation.

5 filings

How payments have changed

Late payments down 36 percentage pointsCompared with the previous filing

Colt Data Centre Services UK Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H1 240%37.5%75%0d45d90dH1 24H2 24H1 25H2 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
View 5 recent filings
Recent payment filings by Colt Data Centre Services UK Ltd
Period endingDays to payPaid lateWithin 30 daysOver 60 days
30 June 20263426%50%5%
31 December 20258062%24%48%
30 June 20254717%36%8%
31 December 20244516%33%4%
30 June 20244419%33%5%

More from the filing

Payment terms and invoice breakdown
Standard payment terms
0 to 90 days
Maximum contractual period
90 days
Paid within 30 days
50%
Paid in 31–60 days
45%
Paid after 60 days
5%
Not paid because of a dispute
0%

The company’s own wording

The Company’s standard contractual payment terms for all qualifying contracts are 60 days from invoice date, however, specific terms can be negotiated and agreed with a supplier. Where applicable, the Company complies with the payment provisions of the Housing Grants, Construction and Regeneration Act 1996. The agreed payment terms are reflected in our contractual documentation and accounting system.
RetentionNone declared

No retention clauses were declared in this filing.

Common questions

How long does Colt Data Centre Services UK Ltd take to pay its suppliers?

Colt Data Centre Services UK Ltd reported an average of 34 days to pay an invoice for 1 January 2026 to 30 June 2026, with 50% of invoices paid within 30 days and 5% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.

Does Colt Data Centre Services UK Ltd pay late?

By its own filing, 26% of Colt Data Centre Services UK Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is down 36 points on its previous filing (62% for the period to 31 December 2025).

Does Colt Data Centre Services UK Ltd hold retention?

Colt Data Centre Services UK Ltd declares no retention clauses in its construction contracts in this filing. Your subcontract governs; if it holds retention, the contract terms decide when it is released.

Can I charge Colt Data Centre Services UK Ltd interest on a late invoice?

Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.