Cbre Gws Ltd: how it pays its suppliers, from its own filing

Cbre Gws Ltd reports paying its suppliers in an average of 57 days, with 32% of invoices paid later than the agreed terms, for the period 1 January 2026 to 30 June 2026. Across the 1,496 companies that report on construction contracts, the median is 31 days and 14% late. Every figure below is the company’s own, approved by a director and published on the government register; this page reproduces it and says what it means for a subcontractor.

57 days

Average days to pay

longer than 91% of the 1,496 filers; median 31 days

32%

Paid later than agreed

a higher share than 82% of filers; median 14%

18%

Paid within 30 days

24% took longer than 60 days

The terms it declares

Standard payment terms
0 to 90 days
Maximum contractual period
90 days
Paid in 31 to 60 days
58%
Paid after 60 days
24%
Not paid because of a dispute
0%
Filed on
29 July 2026

Their standard terms, in their words

60 days NET

Their explanation

WCP program in place for preferred suppliers which results in payment terms of 45 days.

Every filing since Dec 2023

Cbre Gws Ltd has filed 6 times. The share paid late is up 16 points on the previous filing, and the average days to pay down 2 days. The first filing, for the period to 31 December 2023, reported 57 days and 41% late.

Cbre Gws Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H2 230%25%50%0d45d90dH2 23H1 24H2 24H1 25H2 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
The last six filings by Cbre Gws Ltd
Period toDays to payPaid lateWithin 30 daysOver 60 days
30 June 20265732%18%24%
31 December 20255916%21%23%
30 June 20256113%20%24%
31 December 20246319%21%24%
30 June 20246130%27%23%
31 December 20235741%31%30%

Retention

This filing declares no retention clauses in its construction contracts. If your subcontract with Cbre Gws Ltd does hold retention, the contract governs; the retention piece explains how to get it released.

What this means if you are pricing work for them

The share paid later than agreed is the number to read first, because a short term makes an invoice late sooner and a long one hides lateness inside the term. Cbre Gws Ltd is above the median on that measure, so build the delay into your cash flow before you sign. The average days to pay sits over the median.

A worked example on a 30-day term: an invoice of £10,000.00 paid on this company’s average, 27 days after the final date, carries £86.92 of statutory interest at 11.75% plus the fixed sum, £186.92 in all, which the law lets you add without a clause. Run your own figures.

Against the official benchmark: the Department for Business and Trade’s statistics for 2025, published 14 July 2026, put large construction businesses at 33 days to pay with 14% of invoices late by number (13% by value), and all large businesses at 32 days and 15% late. Cbre Gws Ltd is slower than the sector figure. Its late share is above the sector figure.

What the register does not show: it is self-reported, large companies only, and the filing covers the whole company, not your contract. Read it alongside the notice rules that decide what you are actually owed, and keep your own dates.

Questions subcontractors ask about Cbre Gws Ltd

How long does Cbre Gws Ltd take to pay its suppliers?
Cbre Gws Ltd reported an average of 57 days to pay an invoice for 1 January 2026 to 30 June 2026, with 18% of invoices paid within 30 days and 24% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
Does Cbre Gws Ltd pay late?
By its own filing, 32% of Cbre Gws Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 16 points on its previous filing (16% for the period to 31 December 2025).
Does Cbre Gws Ltd hold retention?
Cbre Gws Ltd declares no retention clauses in its construction contracts in this filing. Your subcontract governs; if it holds retention, the contract terms decide when it is released.
Can I charge Cbre Gws Ltd interest on a late invoice?
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.

Source: the company’s own report on the government’s payment practices service, report 114726, made under the Reporting on Payment Practices and Performance Regulations 2017 and reproduced under the Open Government Licence v3.0. Register copy taken 2 October 2026; comparisons are against the latest filing of each of the 1,496 companies declaring construction contracts. Figures are as filed, not judged. Not legal advice.