Carter Synergy Ltd: how it pays its suppliers, from its own filing

Carter Synergy Ltd reports paying its suppliers in an average of 54 days, with 22% of invoices paid later than the agreed terms, for the period 1 January 2026 to 30 June 2026. Across the 1,496 companies that report on construction contracts, the median is 31 days and 14% late. Every figure below is the company’s own, approved by a director and published on the government register; this page reproduces it and says what it means for a subcontractor.

54 days

Average days to pay

longer than 89% of the 1,496 filers; median 31 days

22%

Paid later than agreed

a higher share than 65% of filers; median 14%

7%

Paid within 30 days

41% took longer than 60 days

The terms it declares

Standard payment terms
7 to 90 days
Maximum contractual period
90 days
Paid in 31 to 60 days
52%
Paid after 60 days
41%
Not paid because of a dispute
15%
Filed on
22 July 2026

Their standard terms, in their words

We have very few payment terms of 7 days from invoice date. For the majority of our invoices our payment terms are either 30 days (end of month) or 60 days end of month. For the 60 days end of month the longest payment term could be, if the invoice was dated on the 1st, 90 days form invoice date. Hence 90 has been put in as our longest standard payment terms (which 3 months less one day).

Every filing since Jun 2018

Carter Synergy Ltd has filed 17 times. The share paid late is up 11 points on the previous filing, and the average days to pay unchanged. The first filing, for the period to 30 June 2018, reported 50 days and 9% late.

Carter Synergy Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H1 180%25%50%0d45d90dH1 18H1 19H1 20H1 21H1 22H1 23H1 24H1 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
The last six filings by Carter Synergy Ltd
Period toDays to payPaid lateWithin 30 daysOver 60 days
30 June 20265422%7%41%
31 December 20255411%11%38%
30 June 20255413%10%35%
31 December 20245313%11%37%
30 June 20245710%9%43%
31 December 20235812%9%43%

Retention

This filing declares no retention clauses in its construction contracts. If your subcontract with Carter Synergy Ltd does hold retention, the contract governs; the retention piece explains how to get it released.

What this means if you are pricing work for them

The share paid later than agreed is the number to read first, because a short term makes an invoice late sooner and a long one hides lateness inside the term. Carter Synergy Ltd is above the median on that measure, so build the delay into your cash flow before you sign. The average days to pay sits over the median.

A worked example on a 30-day term: an invoice of £10,000.00 paid on this company’s average, 24 days after the final date, carries £77.26 of statutory interest at 11.75% plus the fixed sum, £177.26 in all, which the law lets you add without a clause. Run your own figures.

Against the official benchmark: the Department for Business and Trade’s statistics for 2025, published 14 July 2026, put large construction businesses at 33 days to pay with 14% of invoices late by number (13% by value), and all large businesses at 32 days and 15% late. Carter Synergy Ltd is slower than the sector figure. Its late share is above the sector figure.

What the register does not show: it is self-reported, large companies only, and the filing covers the whole company, not your contract. Read it alongside the notice rules that decide what you are actually owed, and keep your own dates.

Questions subcontractors ask about Carter Synergy Ltd

How long does Carter Synergy Ltd take to pay its suppliers?
Carter Synergy Ltd reported an average of 54 days to pay an invoice for 1 January 2026 to 30 June 2026, with 7% of invoices paid within 30 days and 41% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
Does Carter Synergy Ltd pay late?
By its own filing, 22% of Carter Synergy Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 11 points on its previous filing (11% for the period to 31 December 2025).
Does Carter Synergy Ltd hold retention?
Carter Synergy Ltd declares no retention clauses in its construction contracts in this filing. Your subcontract governs; if it holds retention, the contract terms decide when it is released.
Can I charge Carter Synergy Ltd interest on a late invoice?
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.

Source: the company’s own report on the government’s payment practices service, report 113305, made under the Reporting on Payment Practices and Performance Regulations 2017 and reproduced under the Open Government Licence v3.0. Register copy taken 2 October 2026; comparisons are against the latest filing of each of the 1,496 companies declaring construction contracts. Figures are as filed, not judged. Not legal advice.