Supplier payment record · 01822941

Cambus Ltd

Reported period: –

View the government filing

Average time to pay

37 days

Register median: 31 days

Invoices paid late

13%

Register median: 14%

Standard payment terms

7 to 60 days

Declared in this filing

These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.

Already waiting for payment?

Check your own invoice.

Use your amount and dates to estimate late-payment interest and fixed compensation.

18 filings

How payments have changed

Late payments up 3 percentage pointsCompared with the previous filing

Cambus Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H2 170%12.5%25%0d30d60dH2 17H2 18H2 19H2 20H2 21H2 22H2 23H2 24H2 25H1 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
View 6 recent filings
Recent payment filings by Cambus Ltd
Period endingDays to payPaid lateWithin 30 daysOver 60 days
2 May 20263713%28%2%
3 November 20254210%27%6%
3 May 2025364%34%2%
27 October 2024354%34%1%
27 April 2024344%36%1%
30 October 2023348%45%3%

More from the filing

Payment terms and invoice breakdown
Standard payment terms
7 to 60 days
Maximum contractual period
60 days
Paid within 30 days
28%
Paid in 31–60 days
70%
Paid after 60 days
2%
Not paid because of a dispute
8%

The company’s own wording

It is the Company’s policy to agree appropriate terms of payment with suppliers for each transaction or series of transactions, and to abide by those terms based on the timely submission of satisfactory invoices. The Company normally settles trade payables on 30 day terms, however variations to these terms do exist based on agreements with certain suppliers.
RetentionNone declared

No retention clauses were declared in this filing.

Common questions

How long does Cambus Ltd take to pay its suppliers?

Cambus Ltd reported an average of 37 days to pay an invoice for 4 November 2025 to 2 May 2026, with 28% of invoices paid within 30 days and 2% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.

Does Cambus Ltd pay late?

By its own filing, 13% of Cambus Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 3 points on its previous filing (10% for the period to 3 November 2025).

Does Cambus Ltd hold retention?

Cambus Ltd declares no retention clauses in its construction contracts in this filing. Your subcontract governs; if it holds retention, the contract terms decide when it is released.

Can I charge Cambus Ltd interest on a late invoice?

Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.