Skip to content
fulcrum
Contact
filing to 31 August 2026

// payment practices, as filed · company 00701982

Bowmer and Kirkland Ltd: how it pays its suppliers, from its own filing

Bowmer and Kirkland Ltd reports paying its suppliers in an average of 28 days, with 12% of invoices paid later than the agreed terms, for the period 1 March 2026 to 31 August 2026. Across the 1,496 companies that report on construction contracts, the median is 31 days and 14% late. Every figure below is the company’s own, approved by a director and published on the government register; this page reproduces it and says what it means for a subcontractor.

28 days

Average days to pay

longer than 38% of the 1,496 filers; median 31 days

12%

Paid later than agreed

a higher share than 43% of filers; median 14%

84%

Paid within 30 days

4% took longer than 60 days

The terms it declares

Standard payment terms
21 to 30 days
Maximum contractual period
30 days
Paid in 31 to 60 days
12%
Paid after 60 days
4%
Not paid because of a dispute
0%
Filed on
24 September 2026

Their standard terms, in their words

Suppliers : 30 days following tax point of invoice Subcontractors : Standard JCT/NEC contract terms

Every filing since Feb 2018

Bowmer and Kirkland Ltd has filed 18 times. The share paid late is down 3 points on the previous filing, and the average days to pay up 1 days. The first filing, for the period to 28 February 2018, reported 41 days and 51% late.

Bowmer and Kirkland Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H1 180%37.5%75%0d30d60dH1 18H1 19H1 20H1 21H1 22H1 23H1 24H1 25H1 26H2 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
The last six filings by Bowmer and Kirkland Ltd
Period toDays to payPaid lateWithin 30 daysOver 60 days
31 August 20262812%84%4%
28 February 20262715%80%4%
31 August 20253117%68%4%
28 February 20253119%65%5%
31 August 20243119%66%4%
29 February 20243127%60%4%

Retention

Retention clauses in construction contracts
yes
Standard retention rate
5%
In all construction contracts
yes
Same terms they receive from their own client
no

What this means if you are pricing work for them

The share paid later than agreed is the number to read first, because a short term makes an invoice late sooner and a long one hides lateness inside the term. Bowmer and Kirkland Ltd is at or below the median on that measure. The average days to pay sits under the median.

On a 30-day term this company’s average lands inside the term, so a late invoice is the exception. When one is late, the calculator shows what statutory interest and the fixed sum add, which the law lets you charge without a clause.

Against the official benchmark: the Department for Business and Trade’s statistics for 2025, published 14 July 2026, put large construction businesses at 33 days to pay with 14% of invoices late by number (13% by value), and all large businesses at 32 days and 15% late. Bowmer and Kirkland Ltd is at or inside the sector figure on days. Its late share is at or below the sector figure.

What the register does not show: it is self-reported, large companies only, and the filing covers the whole company, not your contract. Read it alongside the notice rules that decide what you are actually owed, and keep your own dates.

Questions subcontractors ask about Bowmer and Kirkland Ltd

How long does Bowmer and Kirkland Ltd take to pay its suppliers?
Bowmer and Kirkland Ltd reported an average of 28 days to pay an invoice for 1 March 2026 to 31 August 2026, with 84% of invoices paid within 30 days and 4% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
Does Bowmer and Kirkland Ltd pay late?
By its own filing, 12% of Bowmer and Kirkland Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is down 3 points on its previous filing (15% for the period to 28 February 2026).
Does Bowmer and Kirkland Ltd hold retention?
Yes. Bowmer and Kirkland Ltd declares retention clauses in its construction contracts at a standard rate of 5%, in all of them. The filing's own wording is quoted above.
Can I charge Bowmer and Kirkland Ltd interest on a late invoice?
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.

Source: the company’s own report on the government’s payment practices service, report 116964, made under the Reporting on Payment Practices and Performance Regulations 2017 and reproduced under the Open Government Licence v3.0. Register copy taken 2 October 2026; comparisons are against the latest filing of each of the 1,496 companies declaring construction contracts. Figures are as filed, not judged. Not legal advice.