Average time to pay
42 days
Register median: 31 days
Supplier payment record · 01362615
Reported period: –
View the government filing42 days
Register median: 31 days
28%
Register median: 14%
30 days
Declared in this filing
These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.
Already waiting for payment?
Use your amount and dates to estimate late-payment interest and fixed compensation.
13 filings
Late payments up 15 percentage pointsCompared with the previous filing
| Period ending | Days to pay | Paid late | Within 30 days | Over 60 days |
|---|---|---|---|---|
| 31 March 2026 | 42 | 28% | 32% | 34% |
| 31 March 2024 | 39 | 13% | 38% | 19% |
| 30 September 2023 | 41 | 12% | 34% | 21% |
| 31 March 2023 | 42 | 13% | 34% | 22% |
| 30 September 2022 | 42 | 13% | 32% | 20% |
| 31 March 2022 | 40 | 12% | 35% | 17% |
Our business standard payment terms are between 30 and 60 days. All vendors are paid on a bi- weekly payment run, apart for Major Reciprocal suppliers where payment terms are aligned and payments are made at the end of the calendar month. Invoice payment cycles are weekly on Wednesday and Friday and include cleared and posted invoices up to the invoice due date. This ensures our Suppliers receive payments on time aligned with their commerical terms. Our payment cycles were updated in Janauary 2025, this coincided with implementation of a new Finance and P2P system . This change is appli…
No retention clauses were declared in this filing.
Biffa Landfill Solutions Ltd reported an average of 42 days to pay an invoice for 1 October 2025 to 31 March 2026, with 32% of invoices paid within 30 days and 34% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
By its own filing, 28% of Biffa Landfill Solutions Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 15 points on its previous filing (13% for the period to 31 March 2024).
Biffa Landfill Solutions Ltd declares no retention clauses in its construction contracts in this filing. Your subcontract governs; if it holds retention, the contract terms decide when it is released.
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.