Average time to pay
30 days
Register median: 31 days
Supplier payment record · 00604574
Reported period: –
View the government filing30 days
Register median: 31 days
28%
Register median: 14%
7 to 60 days
Declared in this filing
These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.
Already waiting for payment?
Use your amount and dates to estimate late-payment interest and fixed compensation.
18 filings
Late payments down 12 percentage pointsCompared with the previous filing
| Period ending | Days to pay | Paid late | Within 30 days | Over 60 days |
|---|---|---|---|---|
| 30 June 2026 | 30 | 28% | 67% | 5% |
| 31 December 2025 | 30 | 40% | 65% | 11% |
| 30 June 2025 | 26 | 33% | 70% | 2% |
| 31 December 2024 | 31 | 17% | 79% | 3% |
| 30 June 2024 | 27 | 12% | 68% | 1% |
| 31 December 2023 | 26 | 11% | 77% | 1% |
In respect of any contracts for goods and/or services where Barratt Redrow PLC is the contracting entity it will pay for such goods/services on the last working day of the month following the month in which the goods and services are delivered provided always that it has been correctly invoiced by the Supplier and has received the invoice by the last working day of the month in which the goods/services were delivered. If PLC has not been correctly invoiced by this date, payment shall be made on the last working day of the month following the month in which it has been correctly invoiced by t…
No retention clauses were declared in this filing.
Barratt Redrow PLC reported an average of 30 days to pay an invoice for 1 January 2026 to 30 June 2026, with 67% of invoices paid within 30 days and 5% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.
By its own filing, 28% of Barratt Redrow PLC's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is down 12 points on its previous filing (40% for the period to 31 December 2025).
Barratt Redrow PLC declares no retention clauses in its construction contracts in this filing. Your subcontract governs; if it holds retention, the contract terms decide when it is released.
Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.