Supplier payment record · 00839354

Altrad Babcock Ltd

Reported period: –

View the government filing

Average time to pay

60 days

Register median: 31 days

Invoices paid late

63%

Register median: 14%

Standard payment terms

7 to 91 days

Declared in this filing

These are company-wide, self-reported figures—not a prediction for your invoice. Comparisons use the latest filings of 1,496 companies declaring construction contracts.

Already waiting for payment?

Check your own invoice.

Use your amount and dates to estimate late-payment interest and fixed compensation.

17 filings

How payments have changed

Late payments up 21 percentage pointsCompared with the previous filing

Altrad Babcock Ltd: share of invoices paid late (bars) and average days to pay (line), every filing since H1 180%37.5%75%0d45d90dH1 18H1 19H1 20H1 21H1 22H1 23H2 24H2 25H2 26BARS: PAID LATER THAN AGREEDLINE: AVERAGE DAYS TO PAY
View 6 recent filings
Recent payment filings by Altrad Babcock Ltd
Period endingDays to payPaid lateWithin 30 daysOver 60 days
31 August 20266063%29%30%
28 February 20265742%29%25%
31 August 20256151%24%35%
28 February 20257456%6%69%
31 August 20248039%10%49%
29 February 20247645%7%61%

More from the filing

Payment terms and invoice breakdown
Standard payment terms
7 to 91 days
Maximum contractual period
91 days
Paid within 30 days
29%
Paid in 31–60 days
41%
Paid after 60 days
30%
Not paid because of a dispute
31%

The company’s own wording

60 Days

The company’s explanation

n/a
RetentionNone declared

No retention clauses were declared in this filing.

Common questions

How long does Altrad Babcock Ltd take to pay its suppliers?

Altrad Babcock Ltd reported an average of 60 days to pay an invoice for 1 March 2026 to 31 August 2026, with 29% of invoices paid within 30 days and 30% taking longer than 60 days. The official 2025 figure for large construction businesses is 33 days.

Does Altrad Babcock Ltd pay late?

By its own filing, 63% of Altrad Babcock Ltd's invoices were paid later than the agreed terms, against 14% across large construction businesses in 2025 and a median of 14% among the 1,496 companies on this register that declare construction contracts. That is up 21 points on its previous filing (42% for the period to 28 February 2026).

Does Altrad Babcock Ltd hold retention?

Altrad Babcock Ltd declares no retention clauses in its construction contracts in this filing. Your subcontract governs; if it holds retention, the contract terms decide when it is released.

Can I charge Altrad Babcock Ltd interest on a late invoice?

Yes, under the Late Payment of Commercial Debts (Interest) Act 1998, from the day after the final date for payment, at 8% over the Bank of England base rate plus a fixed sum per invoice, without any clause in the contract. The calculator works it out for your figures.